Cold Water Distribution for External Cooler System

Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

Estudo de Caso Nº

115

Cliente

Chip Manufacturer
Israel

|

2022

Condições de Trabalho

Pressure: 6 bars | Temperature: 8°C / 46°F

Solução Pexgol

Pexgol 355 (14″), 400 (16″) & 630 (24″) mm, Class 15

Aplicação

External Chiller System

Comprimento

160 m / 525 ft

Categorias

Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

The Challenge

A semiconductor chip manufacturer company located in Israel, needed to increase the capacity of energy in the factory by adding an external chiller system and they needed to finish the installation and implementation as soon as possible.

Pexgol Solution

Due to a successful experience in the past, the company decided to use Pexgol pipes due to the fast installation time, helping to maintain their operation schedule and reduce the total cost of the project.

Estudos de Caso Relacionados

Successful outcome in pilot test for SCT Discharge Line with Pexgol.

Advanced piping solutions for handlingscaling fluids

Barrick Gold
Dominican Republic

 | 

2023
Transport of Drinking Water in Harsh Terrain.

Potable Water Aqueduct

Acueducto y Alcantarillado de Bogotá
Colombia

 | 

2019
The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

Cold Water Distribution for External Cooler System

Chip Manufacturer
Israel

 | 

2022
Installation of Buried Pipes to Transport Water on a Mining Road.

Water Transportation on a Mining Road

CODELCO – Andina Mine
Chile

 | 

2019
Replacing HDPE pipes with Pexgol allowed Vale to simplify operations, eliminate auxiliary equipment, and achieve a permanent installation under extreme conditions.

Comprehensive Redesign of the PumpingSystem with Pexgol at the Sossego Mine

Vale
Brazil

 | 

2024