Water Transportation on a Mining Road

Installation of Buried Pipes to Transport Water on a Mining Road.

Estudo de Caso Nº

79

Cliente

CODELCO – Andina Mine
Chile

|

2019

Condições de Trabalho

Extreme temperatures -20° to 35°C / -4° to 95°F

Solução Pexgol

Pexgol 355 mm (14”), class 19

Aplicação

Dewatering

Comprimento

1700 m / 5577 ft

Categorias

Installation of Buried Pipes to Transport Water on a Mining Road.

The Challenge

CODELCO required to transport water in an open pit mine section, destined for a pool located on the south side.

The job had to be done quickly to avoid damage to the access road. Therefore the pipeline should be located on the side of the road, buried.

Pexgol Solution

The client chose Pexgol because it was impossible to meet the delivery terms of the pipeline enabled with another type of pipe.
The advantage of Pexgol, in this solution, lies in the supply format in coils of long lengths and the possibility of burying it without the need for a sand enbeding. In addition, the pipeline was guaranteed to withstand strong temperature variations over the course of a year, ranging from -20°C to 35°C / -4°F to 95°F.

The installation was simple and fast. Crosspipe Systems carried out a complete induction to the pipe installation company, both in the uncoiling and in the welding of the couplings. In total 35 electrofusion couplings were made.

Estudos de Caso Relacionados

Groundwater Transportation With Ph Low Levels

Groundwater Transportation

Grupo México, Buena Vista del Cobre Mine
Mexico

 | 

2015
Pexgol helped Profertil to overcome the corrosion challenge in its fire protection network.

From carbon steel to Pexgol: A victory against corrosion

Profertil
Argentina

 | 

2021
Replacement of Titanium Pipes by Pexgol Pipes to Transport Acid Solution.

Process Plant: Transport of Leached Slurry

Barrick Gold – Pueblo Viejo
Dominican Republic

 | 

2018
Cement Slurry Injection to an Underground Mine

Backfill

Aguilar Mine
Argentina

 | 

2015
Replacement Of PVC Piping for PE-X in a Industrial Heating System.

Transport of Hot Air for Advanced Agriculture

Teva Post
Israel

 | 

2022
Installation of a Pexgol Pipe on top of a Steel Outdated Pipe

Carriage of Chemicals at Sea Port

Ashdod Sea Port
Israel

 | 

2016