Drinking Water on Sloping Terrain

Installation of a drainage system between a well and a mining dam.

Estudo de Caso Nº

84

Cliente

AquaMag
Colombia

|

2019

Condições de Trabalho

Temperature: ambient | Pressure: 3 bar | Sloping terrain

Solução Pexgol

Pexgol 160 mm (6″), class 10

Aplicação

Potable water transport

Comprimento

188 m

Categorias

Installation of a drainage system between a well and a mining dam.

The Challenge

AquaMag, the aqueduct and sewerage company of Santa Rosa de Lima (Colombia), uses pipes that are exposed on the lands or farms of the inhabitants of this population to transport raw water for treatment. Due to uncontrolled agricultural burning on the farms, a section of the existing HDPE pipe was burned.

AquaMag needed to continue supplying drinking water to 1,600 people, transporting 10 liters per second, from the San Sebastián river to Santa Rosa de Lima.

The Solution

The client ultimately decided to install a Pexgol pipe due to its ease of handling on complex terrain, resistance to wear, UV rays (since the pipe was exposed), longer life compared to other materials, and the ability to supply it in rolls, which allowed for fewer joints.

Due to the terrain conditions, the installation took 10 days, which would have taken 25 days if another type of pipe had been used.

43 electrofusion joints were made, as sections of HDPE pipe were replaced by Pexgol in different areas. In critical points, a complete section of Pexgol pipe was used.

Estudos de Caso Relacionados

Transport of high corrosive material from the thickeners to the neutralization plant

Corrosive Material Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2015
Replacement of Steel Pipes with Pexgol for Testing Centrifugal Pumps.

Pexgol for Centrifugal Pump Test

Flowserve
Argentina

 | 

2022
Installation of Buried Pipes to Transport Water on a Mining Road.

Water Transportation on a Mining Road

CODELCO – Andina Mine
Chile

 | 

2019
Installation of Pexgol Pipes to Transport Fish.

Fish Discharge Lines

TASA
Peru

 | 

2018

Categories:

Installation of Pexgol Pipe for the Transport of Abrasive Tailings.

Abrasive Tailings Transport

Pirquitas Mine
Argentina

 | 

2015
Transportation of water in more than 150 mining crossroads

Water Transport on Crossroads

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2012