Slurry Transportation

Replacement of a HDPE Pipe for a Pexgol Pipe

Estudo de Caso Nº

40

Cliente

Sabinas Mine
Mexico

|

2017

Condições de Trabalho

Discharge by gravity, ambient temperature, abrasive fluid.

Solução Pexgol

Pexgol SDR 15 225 x 20.4.

Aplicação

Slurry transportation.

Comprimento

1642 meters.

Categorias

Replacement of a HDPE Pipe for a Pexgol Pipe

The Challenge

The client required to replace their current HDPE pipe lines where they transported slurry since they have frequent wear and leak issues on the joints. They used thermo-fusion welding, plus reinforcement with a Vitaulic 995 coupler. This sort of situation involved a considerable expense every time they failed, but they didn’t last long. The failures were every 3 to 4 months.

Pexgol Solution

In order to perform a better job when transporting slurry, the client decided to install a Pexgol pipe of 1642 meters SDR 15 225 x 20.4.

Thanks to Pexgol’s comprehensive piping solution, abrasion issues were avoided, since its cross-linked material is between 4 to 10 times more resistant than other pipes materials.

The pipes were supplied n sections up to 240 meters each one, consequently the installation was simple improving the process’s security and therefore protecting the environment.

Estudos de Caso Relacionados

Replacing Steel for PE-X Pipes to Transported Processed Water.

Replacement of Steel Pipes for PE-X

Rosebel Gold Mines – IamGold
Suriname

 | 

2020
Química del Rey replaced a corroded steel column with a Pexgol line, achieving a faster, safer, and more durable installation.

Reliable Solution for Deep Wells in Corrosive Environments

Química del Rey
Mexico

 | 

2022
Field evaluation of Pexgol PE-Xa pipes under highly abrasive iron ore slurry conditions at Cauê Mine.

Test Case – Field Performance Evaluation of Pexgol

Vale
Brazil

 | 

2025
Installation of a Drainage System in an Open Pit Mine.

Drainage System

BHP Pampa Norte – Cerro Colorado Mine
Chile

 | 

2020
Bridging the Gap between Durability and Functionality in Harsh Processing Environments.

Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport

Syncrude
Canada

 | 

2022
Transport of Muddy Water (Pome) witha High Content of Organic Load.

Transport of Muddy Water in a Palm Oil Processing Plant

La Gloria
Colombia

 | 

2020