Slurry Transportation

Replacement of a HDPE Pipe for a Pexgol Pipe

Estudo de Caso Nº

40

Cliente

Sabinas Mine
Mexico

|

2017

Condições de Trabalho

Discharge by gravity, ambient temperature, abrasive fluid.

Solução Pexgol

Pexgol SDR 15 225 x 20.4.

Aplicação

Slurry transportation.

Comprimento

1642 meters.

Categorias

Replacement of a HDPE Pipe for a Pexgol Pipe

The Challenge

The client required to replace their current HDPE pipe lines where they transported slurry since they have frequent wear and leak issues on the joints. They used thermo-fusion welding, plus reinforcement with a Vitaulic 995 coupler. This sort of situation involved a considerable expense every time they failed, but they didn’t last long. The failures were every 3 to 4 months.

Pexgol Solution

In order to perform a better job when transporting slurry, the client decided to install a Pexgol pipe of 1642 meters SDR 15 225 x 20.4.

Thanks to Pexgol’s comprehensive piping solution, abrasion issues were avoided, since its cross-linked material is between 4 to 10 times more resistant than other pipes materials.

The pipes were supplied n sections up to 240 meters each one, consequently the installation was simple improving the process’s security and therefore protecting the environment.

Estudos de Caso Relacionados

Pexgol’s Role in Enhancing Guaymas Protein’s Operations.

Transition to Corrosion-Free Diesel Delivery Systems

Guaymas Protein
Mexico

 | 

2023
Installation of a Drainage System between a Well and a Mining Dam.

Well Drainage at Mining Dam

CODELCO – El Teniente Mine
Chile

 | 

2019
O sistema de tubulação da Pexgol permitiu que a Nexa Resources renovasse seu processo de gerenciamento de resíduos, reduzindo significativamente o impacto ambiental.

Aprimorando a Gestão de Resíduos da Nexa Resources Usando Pexgol

Nexa Resources
Brasil

 | 

2023
Transport of acid water at high temperatures

Water Transport with Low pH Level

Moa Nickel S.A. Sherritt
Cuba

 | 

2010
Transport of Formation Water with Hydrocarbons.

Formation Water Transport

ROCH
Argentina

 | 

2015
Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Hot & Abrasive Potash Brine Processing

Fertilizer Company
Canada

 | 

2017