Carriage of Chemicals at Sea Port

Installation of a Pexgol Pipe on top of a Steel Outdated Pipe

Estudo de Caso Nº

50

Cliente

Ashdod Sea Port
Israel

|

2016

Condições de Trabalho

High pressure, abrasion, constant water hammers

Solução Pexgol

Pexgol 315 mm 90 Class 12 SDR 16.3

Aplicação

Chemicals Transportation

Comprimento

1.3 km

Categorias

Installation of a Pexgol Pipe on top of a Steel Outdated Pipe

The Challenge

Commonly at Ashdod Sea Port (Israel) they require to transport all kinds of chemicals, acids and slurries to ship for export, from the port to the shipping boats.

In order to fulfill this procedure they installed cast steel pipes, which suffer from corrosion inside the pipe due to the chemicals after so many years carrying them. This steel pipes were very expensive to maintain, including frequent cleaning.

Pexgol Solution

An engineering firm specializing in the chemical industry, stated that Pexgol was the ideal solution for dealing with the challenges of the
line:

  • Pexgol’s proven ability to deal with acids.
  • Durability of the pipes.
  • The possibility of installing a 315 mm continuous pipe line without flanged connections in curved sections, saving the number of flanges and dramatically reducing weak points.

The Pexgol pipes were installed hanging with fixpoints on top of the current steel pipes, without damaging them. Omegas were installed as well (that couldn’t be done with PE pipes).
Took 10 days to install and operate the line, having the ships waiting in the water, the line started working immediately after completion.

Estudos de Caso Relacionados

Water Drainage in Harsh Ground

Water Drainage at an Open-Cast Mine

Timmins Gold Corp Group, Molimentales del Noroeste Mine
Mexico

 | 

2016
Water Transportation through Shafts

Open Cast Mine Dewatering

Agnico Eagle Pinos Altos Mine
Mexico

 | 

2017
Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

Pumping Mining Effluents

AngloGold Ashanti
Brazil

 | 

2019
The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
Installation of Pexgol Pipe for Transportation of Mining Tailings.

Tailings Transport with 50% solids

Golden Resource Corp. – Don David Gold Mine
Mexico

 | 

2019