Skip to content

Drainage in Underground Mine

Replacement of a Drainage Line in an Underground Mine.

Estudo de Caso Nº

74

Cliente

Atacama Kozan
Chile

|

2019

Condições de Trabalho

Underground work

Solução Pexgol

Pexgol 160 mm (6”), class 10, 15, 19, 24 & 30

Aplicação

Dewatering

Comprimento

3573 m / 11722.44 ft

Categorias

Replacement of a Drainage Line in an Underground Mine.

The Challenge

Atacama Kozan, a mining company engaged in the production of high-purity copper concentrate in the Atacama region (Chile), required to
change one of the two lines in the mine’s main drainage system. They need a pipeline with a non-invasive installation to make sure the mining operation was able to continue working in the shortest time possible.

Pexgol Solution

The client decided to install 3,573 meters of Pexgol 160 mm pipe in different classes: 10, 15, 19, 24 and 30. They chose to use cross-linked polyethylene due to:

  • Savings in time and costs due to its long-length supply format with fewer joints.
  • Ease of installation, thanks to the flexibility of the pipe that was able to be accommodated without problems in the curves of the interior of the mine.
  • Limited installation times to avoid stopping the mining operation.
  • Cost savings by optimizing and selecting the pipeline laying according to the pressures and hydraulic profile of the project.

Installation was quick and easy, the pipeline was uncoiled entirety and then dragged into the mine. Eight electrofusion joints were made, in addition, on-site consulting was carried out for the electrofusion work.

Estudos de Caso Relacionados

Pipe installation on a mountain

Meltdown Water Transport

Codelco Andina, TADA 1-2 Project
Chile

 | 

2013
Pexgol helped Profertil to overcome the corrosion challenge in its fire protection network.

From carbon steel to Pexgol: A victory against corrosion

Profertil
Argentina

 | 

2021
Lasta2 Filter Press Feed Lines

Concentrated Copper Transportation

BHP Billiton, Olympic Dam, Australia
Australia

 | 

2014
Installation of 1000 Meters of PE-X Pipe for an Underground Mine.

Mining Drainage Lines

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019
Substitution of a Steel Spool for PE-X Coated for Pumping Formation Water.

Replacement of a Steel Spool with Pexgol

Enap Sipetrol
Ecuador

 | 

2021
Installation of a Drainage System between Dams in a Copper Mine.

Water Transport Between Dams

CODELCO – El Teniente Mine
Chile

 | 

2019