Condições de Trabalho

Fluid: industrial water | Ambient temperature: 5° to 20°C / 41° to 68°F

Solução Pexgol

Pexgol 225 mm (8”), class 15

Aplicação

Open pit mine drainage

Comprimento

200 m / 656 ft

Categorias

Pexgol Pipe Installation for Open Pit Mine Drainage

The Challenge

BHP at its Escondida mining unit needed to drain water from inside its open pit mine to the outside. The client used to use conventional HDPE pipes in 12-meter strips in its operations, which requires long installation times, joints and associated resources.

Pexgol Solution

The client decided to replace its conventional HDPE pipes with Pexgol, which could be supplied in long sections (200 m), which allowed and facilitated installation. Likewise, Pexgol allowed the use of fewer joints for the total section.

An unwinding time of 200 meters was calculated, in 40 minutes set at the end point. The same amount of meters in pipes with strips of 12 meters, they achieved it in 14 days, that is, 20,160 minutes.

Performance

Tubería HDPE= 200 m / 20160 min = 0,6 m/hr
Tubería Pexgol= 200 m / 40 min = 300 m/hr

Pexgol performance 504 times more efficient.

Estudos de Caso Relacionados

Explore how Pexgol pipe replacement addressed the corrosion issue in Gordon Pool’s saltwater delivery system, ensuring efficient operation.

From Steel to Pexgol: A Plumbing Upgrade for Tel Aviv’s Gordon Pool

Gordon Pool
Israel

 | 

2023
The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
How Pexgol piping improved the fire network system infrastructure in a paint manufacturing plant.

Pexgol Piping for Fire Network System Expansion

Wall
Argentina

 | 

2023
Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

Pumping Mining Effluents

AngloGold Ashanti
Brazil

 | 

2019
Mining Effluent Transportation in Cuba.

Pexgol Optimizes Tailings Management at Sherritt’s Moa Nickel Mine

Sherritt
Cuba

 | 

2020