Transport of Palm Oil Slurry

Transport Of Palm Oil Slurry At 95°C.

Estudo de Caso Nº

57

Cliente

Loma Fresca
Colombia

|

2017

Condições de Trabalho

Fluid at 95°C, 2 bar

Solução Pexgol

Pexgol 63 mm, Class 15

Aplicação

Slurry transportation

Comprimento

150 m

Categorias

Transport Of Palm Oil Slurry At 95°C.

The Challenge

Loma Fresca is an agro-industrial company, dedicated to the transformation and commercialization of products derived from the cultivation of African palm oil.

As part of the production process, the client required to transport the waste from the palm, to be discarded later. First, they used a carbon steel pipe. It suffered from serious sedimentation problems until it was completely covered, requiring constant plant stops both for cleaning and for replacing the pipes, thus influencing the costs and production time.

Pexgol Solution

Loma Fresca required a pipe that on one hand could withstand the high temperatures of the fluid and that at the same time have greater resistance to the incrustation versus the steel pipes they formerly had. They needed a quick and effective installation to not have to stop production for a long time.

Loma Fresca decided the acquisition of the Pexgol pipe system. The installation was carried out in a single day. The line was separated by sections of pipes and was connected with electrofusion elbows.

Estudos de Caso Relacionados

Water Transport from a Borehole with Low Ph.

Water transport in textile factory

CMT La Laguna
Mexico

 | 

2018
Replacing steel pipes suffering from sediment formation

Transportation of Ore Slurry

RUSAL, aluminum factory
Russia

 | 

2012

Categorias:

Acid liquor line with high levels of abrasion and sedimentation

Abrasive Liquid Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2014
Water transportation with sulfide and cobalt particles

Water and Sulfide Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2015
Installation of a Fire Supply Network in a Oil Treatment Plant.

Fire Network Supply

YPF
Argentina

 | 

2021
Installation Oof Pexgol Pipes through a Chimney for Compressed Air.

Transport of Compressed Air for Underground Mine

HMC Gold
Chile

 | 

2021