Skip to content

Greater Efficiency and Safety in Leaching with Pexgol Pipes

Pexgol’s chemical resistance and flexibility outperform HDPE in demanding leach pad operations.

Estudo de Caso Nº

178

Cliente

Barrick Gold Corp.
Argentina

|

2025

Condições de Trabalho

Temperature: -25°C to +35°C| Pressure: 1–2 bar | Flow Rate: 25 m³/h per branch (50 m³/h per pad)| Fluid: Cyanide solution (pH 10)

Solução Pexgol

Pexgol 110 mm, class 10

Aplicação

Cyanide leaching pads for gold and silver recovery

Comprimento

300 m / 984 ft

Categorias

Greater Efficiency and Safety in Leaching with Pexgol Pipes

The Challenge

Barrick Gold Corp., one of the world’s leading producers of gold and silver, operates under extreme environmental conditions at its Veladero project in Argentina. For its cyanide leaching pads, the company traditionally used 8” HDPE pipelines to transport cyanide solutions (pH 10) across wide temperature ranges, from -25°C to +35°C.

The biggest operational challenge stemmed from the irrigation method: after each leaching cycle, the pipelines were dragged manually to the next cell. This caused significant wear and mechanical fatigue, with HDPE pipes failing after just 4–5 uses. Their weight made handling difficult, increasing safety risks for personnel. Additionally, HDPE’s rigidity required a large number of fittings, particularly to navigate the 90×60-meter leaching pads, leading to higher costs and longer installation times.

Barrick sought a lighter, more flexible, and chemically resistant solution capable of withstanding extreme conditions and improving overall efficiency.

The Solution

To address these issues, Barrick replaced the HDPE system with 300 meters of 110 mm Pexgol Class 10 pipe. Pexgol’s exceptional chemical resistance to cyanide solution and its ability to operate at sub-zero temperatures ensured optimal performance under extreme conditions.

The entire system was installed within a single workday, including staff training, on-site transport, and uncoiling in three stages. Thanks to Pexgol’s natural flexibility, bends and changes in direction were made without fittings, which reduced installation time and material costs. Its light weight allowed for easier and safer handling, even during pipe dragging across leach pads.

With fast deployment, high corrosion resistance, and easy roll transport, Pexgol enabled Barrick to improve operational efficiency. The pipe’s long lifespan—even under frequent dragging—made it a superior alternative to HDPE for cyanide leaching in mining applications.

Estudos de Caso Relacionados

Transport of high corrosive material from the thickeners to the neutralization plant

Corrosive Material Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2015
Installation of Pexgol Pipe in a Formation Water Treatment Plant.

Secondary Injection Water Plant

YPF
Argentina

 | 

2020
Test Installation for Transporting Silica Sand.

Transport of Silica Arena: HDPE vs Pexgol

Covia Corp
Mexico

 | 

2019
Pexgol’s resistance to scaling and chemicals delivers consistent operation in open-pit mining.

Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

Buena Vista del Cobre
Mexico

 | 

2024
Pexgol Pipe Installation for Open Pit Mine Drainage.

Efficient Open Pit Mine Drainage

BHP Escondida Mine
Chile

 | 

2022
Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Hot & Abrasive Potash Brine Processing

Fertilizer Company
Canada

 | 

2017