High Corrosion Resistance Against Brine

Pexgol Fittings for Brine Transportation at a Brazilian Chemical Company.

Estudo de Caso Nº

89

Cliente

Unipar Carbocloro
Brazil

|

2019

Condições de Trabalho

Composition: 74,8% NaCl; 0,077% NaOH; 0,002% Na2CO3; 0,853% Na2SO4; 24,33% H2O | Temperature: 77°C / 170.6°F | Flow: 69 m³/h | Pump pressure: 8 kgf/cm²

Solução Pexgol

Pexgol 125 mm (4”), Class 15

Aplicação

Brine

Comprimento

Prefabricated Elbows and Short Sections

Categorias

Pexgol Fittings for Brine Transportation at a Brazilian Chemical Company.

The Challenge

Unipar Carbocloro is a Brazilian chemical company that operates in the soda and chlorine industry. At the outputs of the brine pumps, Carbocloro used to replace its piping components at least once every 6 months. They tried several materials and not one had performed successfully. The last ones were made of nickel and yet did not last more than six months, having leakages all around. The high corrosivity of the media was the main issue to be faced.

Pexgol Solution

Pexgol’s engineering team analyzed the whole situation, suggested a new design using Pexgol pipes and accessories and nowadays the output of the pump has worked non-stop (and with no signs of probable stops) for 9 months already.

The installation, despite the solution being formed by several parts, was easy and quick. Carbocloro’s team simply based the tasks on the plans providaded by the factory.

Estudos de Caso Relacionados

Transport Of Lime Slurry At 100°C

Transport of Lime Slurry

Minas de Oro Nacional, Mulatos Mine
Mexico

 | 

2015
The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Transporting Brine at High Pressure

Mekorot
Israel

 | 

2020
The innovative solution from Pexgol for Anglo American Peru’s piping challenges.

Navigating extreme conditions with Pexgol’s PE-X pipes

Anglo American Perú
Peru

 | 

2023
Reduction of material build-up in brine and brine/acid lines

Mineral Processing – Brine Transportation

SQM,Pedro Valvidia Mine
Chile

 | 

2010
Installation of Pexgol Pipe for Transportation of Mining Tailings.

Tailings Transport with 50% solids

Golden Resource Corp. – Don David Gold Mine
Mexico

 | 

2019