High Pressure Dewatering in Open Pit Mine

Pexgol Pipe Installation for Open Pit Mine Drainage.

Estudo de Caso Nº

102

Cliente

Lundin Mining
Chile

|

2021

Condições de Trabalho

Flow: 720 m3/h

Solução Pexgol

Pexgol 315 mm (12”), Class 32

Aplicação

Open pit mine dewatering

Comprimento

3240 m / 10629 ft

Categorias

Pexgol Pipe Installation for Open Pit Mine Drainage.

The Challenge

Lundin Mining, in its Candelaria Tierra Amarilla mining unit, required the installation of a high-pressure dewatering line from the lower level, passing through mine banks.

Due to time problems, the mining company needed to have a pipeline where its installation would not be invasive for the mining operation and continue working in the shortest period of time possible.

Pexgol Solution

After receiving advice from the local team (Crosspipe Systems) the client decided to install 3240 meters of Pexgol 315 mm class 32 pipe for their mine dewatering system. The project consisted of 5 pumping stations, with dropouts of up to 200 meters between banks, with twin lines of Pexgol 315 mm class 32.

EF couplers, metallic reinforcement and alignment clamps were used for the projection of joints in the dropouts.

Pexgol was selected for its long-length supply format, for its ability to be unhooked from the mine benches and the possibility of providing short installation times, which facilitated assembly and commissioning.

Estudos de Caso Relacionados

Performance evaluation of Pexgol lining under extreme service conditions.

Durable Solution Against Abrasion in Production Facilities: Pexgol at YPF

YPF
Argentina

 | 

2018
Acid liquor line with high levels of abrasion and sedimentation

Abrasive Liquid Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2014
Enhancing Efficiency and Durability in the Construction of Aerial Pipelines.

Facing the Challenges of the Neuquén Terrain in Argentina

Pluspetrol
Argentina

 | 

2023
Overcoming Corrosion Challenges in the Oil Industry

Overcoming Corrosion Challenges in the Oil Industry

Petróleos Sudamericanos
Argentina

 | 

2023
O sistema de tubulação da Pexgol permitiu que a Nexa Resources renovasse seu processo de gerenciamento de resíduos, reduzindo significativamente o impacto ambiental.

Aprimorando a Gestão de Resíduos da Nexa Resources Usando Pexgol

Nexa Resources
Brasil

 | 

2023
A high-precision maneuver enabled the complete assembly of the system in record time, ensuring safety and operational continuity.

Pexgol Overcomes Extreme Dewatering Conditions in La Ciénega

Fresnillo Plc.
Mexico

 | 

2025