Skip to content

Open Cast Mine Dewatering

Water Transportation through Shafts

Estudo de Caso Nº

39

Cliente

Agnico Eagle Pinos Altos Mine
Mexico

|

2017

Condições de Trabalho

300 psi, altitude dierence= 174 m, mine water with 15-20% solids.

Solução Pexgol

Pexgol SDR 7.4 225×30.8.

Aplicação

Dewatering.

Comprimento

225 meters.

Categorias

Water Transportation through Shafts

The Challenge

The ground water control system used at Pinos Altos Mine is trough dewatering, which is the method that better adjust to the characteristics of the mine work, furthermore it’s the more efficient and cost-effective if it’s handled the right way.

The fluid transportation associated costs in the mining industry represents an important percentage of the total cost of the operation, consequently the development of work schemes and a hydraulic system optimization, generates important savings on operational costs.

For the pumping system optimization the client designed a pool on level 28, that will gather the runoff water from the superior levels after pumping up to level 22.

Pexgol Solution

For this conduction line a Pexgol pipe was chosen, since it fulfilled the technical features that the job required. Due its ability to be supplied in long length coils, and its capacity to hold 175 meters of water column (249 psi), plus its easy-to-maneuver and installation capabilities (since the pipe was installed through the shafts) and its supplied long sections (which prevents head losses through the joints), the Pexgol pipe was the perfect solution. In addition, the Pexgol pipe roughness coefficient is lower than other pipes, therefore less friction losses and energy savings were encountered.

Estudos de Caso Relacionados

Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

Cold Water Distribution for External Cooler System

Chip Manufacturer
Israel

 | 

2022
Mining Effluent Transportation in Cuba.

Pexgol Optimizes Tailings Management at Sherritt’s Moa Nickel Mine

Sherritt
Cuba

 | 

2020
Record-time intervention that avoided operational losses in a dehydration plant.

Critical Pipeline Replacement in Dehydration Plant with Operational Continuity

Petróleos Sudamericanos
Argentina

 | 

2025
Test Of Pexgol Pipes Vs Hdpe Pipes For Brine Transportation

Test: Pexgol vs HDPE for Brine Transportation

YBL
Bolivia

 | 

2017
Pexgol: Delivering Rapid, Reliable & Long-lasting Mining Drainage Solutions

Addressing Drainage Challenges with Pexgol

Avino Mine
Mexico

 | 

2023
Reducing maintenance and increasing safety in hydraulic backfill operations.

Pexgol Simplifies Slurry Transportation at Buriticá Mine

Zijin - Continental Gold
Colombia

 | 

2023