Critical Pipeline Replacement in Dehydration Plant with Operational Continuity

Record-time intervention that avoided operational losses in a dehydration plant.

Estudo de Caso Nº

192

Cliente

Petróleos Sudamericanos
Argentina

|

2025

Condições de Trabalho

Temperature: 20°C / 68°F | Pressure: 3 kg/cm² | Fluid components: Water with hydrocarbon content (>2% HC)

Solução Pexgol

Pexgol 250 mm, Class 15

Aplicação

Water transport to dehydration plant (injection for secondary recovery)

Comprimento

10 m / 3.28 ft

Categorias

Critical Pipeline Replacement in Dehydration Plant with Operational Continuity

The Challenge

Petróleos Sudamericanos is an Argentine company dedicated to the exploration and production of hydrocarbons, operating key assets in the Catriel Oeste region.

In this project, the dehydration plant plays a critical role: treated water is used for injection in secondary recovery processes, while oil is conditioned for delivery to refineries. The operation required the continuous transport of a fluid composed mostly of water (98%) with the presence of hydrocarbons (>2%), creating highly aggressive conditions for pipeline materials.

The existing GRP pipeline suffered recurrent failures due to constant corrosion, forcing shutdowns of both the plant and the oilfield for repairs. These stoppages resulted in significant production losses, increased operational costs, and disruptions across the entire transport and dispatch chain.

Additionally, since this was a critical line within the process, any intervention involved high operational and economic risk, as downtime needed to be minimized.

The Solution

To definitively solve the problem, a solution using 250 mm (Class 15) Pexgol pipes was implemented, designed to operate at a pressure of 3 kg/cm² and a temperature of 20°C, with excellent performance in fluids containing hydrocarbons.

The pipeline replacement was executed as a critical operation completed in just two working days. Thanks to the material’s flexibility, availability in long lengths, and ease of installation using electrofusion fittings, intervention time was significantly reduced.

As a result, the oilfield was shut down for only 8 hours, avoiding production losses, idle equipment and labor costs, and the need to reschedule field operations.

The chemical resistance of PE-Xa to hydrocarbons and its immunity to corrosion eliminated the root cause of the problem, ensuring reliable long-term operation. Additionally, the material’s light weight and fast installation enabled efficient execution even in a sensitive operational environment.

This solution not only resolved the immediate issue but also optimized system operational continuity, reducing risks and costs associated with future interventions.

Estudos de Caso Relacionados

Flexible installation, fast deployment and long service life for a mining project with over 300 m of elevation difference

Pexgol Ensures Reliable Operation in High- Demand Hydraulic Systems

Endeavour Silver
Mexico

 | 

2024
High-pressure water transport for the Southern Pit in a copper and zinc mine.

High-pressure fluid transport

Minera Antapaccay
Peru

 | 

2023
Overcoming Corrosion Challenges in the Oil Industry

Overcoming Corrosion Challenges in the Oil Industry

Petróleos Sudamericanos
Argentina

 | 

2023
Pvc Pipe Replacement by Pexgol

Transportation of sodium sulfide

Magnelec S.A. de C.V.
Mexico

 | 

2018
O sistema de tubulação da Pexgol permitiu que a Nexa Resources renovasse seu processo de gerenciamento de resíduos, reduzindo significativamente o impacto ambiental.

Aprimorando a Gestão de Resíduos da Nexa Resources Usando Pexgol

Nexa Resources
Brasil

 | 

2023
The Robust & Flexible Answer to Constantly Changing Mine Surfaces.

Evolving Mine Operations with Pexgol Piping

Peña Colorada
Mexico

 | 

2023