Process Plant: Transport of Leached Slurry

Replacement of Titanium Pipes by Pexgol Pipes to Transport Acid Solution.

Estudo de Caso Nº

62

Cliente

Barrick Gold – Pueblo Viejo
Dominican Republic

|

2018

Condições de Trabalho

Acid solution at 100°C. Chemical Composition: SiO2 64%; Al203 11.25%; As 0.05%; Ca 0.17%; Cr 0.01%; Cu 0.03%; Fe 5.37%; K 0.04%; Mg 0.02%; Na 0.08%; Pb 0.04%; Zn 0.17%

Solução Pexgol

Pexgol 63 mm (2”), Class 15

Aplicação

Slurry transportation

Comprimento

2 m / 6.5 ft flanged sections 45° & 90° prefabricated elbows 100 m / 328 ft coils

Categorias

Replacement of Titanium Pipes by Pexgol Pipes to Transport Acid Solution.

The Challenge

Barrick Gold at the Pueblo Viejo mine was transporting slurry (acid solution) through titanium pipes GR2, SCH80S 2 for the drainage of the autoclaves, using this material due to the combination of low pH and abrasion in the fluid.

When using titanium, the tubes and elbows needed to be replaced on average between 3 and 6 months due to wear.

Pexgol Solution

The team of Pexgol together with the engineers of the Process Plant decided to carry out a test to replace a 2 meter (6.5 ft) section of their titanium pipe.

The first Pexgol pipe was installed at the end of the year 2017. This pipe section is still in operation, surpassing on a large scale the service life with the pipeline used previously.

Given the success of the test, almoust the rest of the line has been replaced, including 45° and 90° prefabricated elbows, thus avoiding plant stoppages and unnecessary losses.

Due to the difference in temperature at the time of installation and the operating conditions, part of the installed tubes suffered the “snake” effect. Due to aesthetic and operational issues, this problem was solved by installing additional support, leaving the tubes straight and firm.
Pexgol pipes resistance to temperature and abrasion combined with the smooth internal surface made the installation a success.

Estudos de Caso Relacionados

Delivering Durability and Flexibility for a Sustainable Approach to Space Access.

Pioneering Space Launches with Ground-breaking Piping Solutions

SpinLaunch
USA

 | 

2021
Water Transport from a Borehole with Low Ph.

Water transport in textile factory

CMT La Laguna
Mexico

 | 

2018
Replacement of HDPE Pipes For Pe-X to Transport Industrial Treated Water.

Industrial Waste Water to MBR Treatment Facility

Chip Manufacturer
Israel

 | 

2021
Pexgol Transforms Tailings Transportation at Minera San Julián.

Minera San Julián Adopts Pexgol to Improve Water Management

Fresnillo plc
Mexico

 | 

2024
Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Transporting Brine at High Pressure

Mekorot
Israel

 | 

2020
Dewatering without Supports

Open Cast Mine Dewatering

El Volcan Mine Arcelor Mittal
Mexico

 | 

2017