Process Plant: Transport of Leached Slurry

Replacement of Titanium Pipes by Pexgol Pipes to Transport Acid Solution.

Estudo de Caso Nº

62

Cliente

Barrick Gold – Pueblo Viejo
Dominican Republic

|

2018

Condições de Trabalho

Acid solution at 100°C. Chemical Composition: SiO2 64%; Al203 11.25%; As 0.05%; Ca 0.17%; Cr 0.01%; Cu 0.03%; Fe 5.37%; K 0.04%; Mg 0.02%; Na 0.08%; Pb 0.04%; Zn 0.17%

Solução Pexgol

Pexgol 63 mm (2”), Class 15

Aplicação

Slurry transportation

Comprimento

2 m / 6.5 ft flanged sections 45° & 90° prefabricated elbows 100 m / 328 ft coils

Categorias

Replacement of Titanium Pipes by Pexgol Pipes to Transport Acid Solution.

The Challenge

Barrick Gold at the Pueblo Viejo mine was transporting slurry (acid solution) through titanium pipes GR2, SCH80S 2 for the drainage of the autoclaves, using this material due to the combination of low pH and abrasion in the fluid.

When using titanium, the tubes and elbows needed to be replaced on average between 3 and 6 months due to wear.

Pexgol Solution

The team of Pexgol together with the engineers of the Process Plant decided to carry out a test to replace a 2 meter (6.5 ft) section of their titanium pipe.

The first Pexgol pipe was installed at the end of the year 2017. This pipe section is still in operation, surpassing on a large scale the service life with the pipeline used previously.

Given the success of the test, almoust the rest of the line has been replaced, including 45° and 90° prefabricated elbows, thus avoiding plant stoppages and unnecessary losses.

Due to the difference in temperature at the time of installation and the operating conditions, part of the installed tubes suffered the “snake” effect. Due to aesthetic and operational issues, this problem was solved by installing additional support, leaving the tubes straight and firm.
Pexgol pipes resistance to temperature and abrasion combined with the smooth internal surface made the installation a success.

Estudos de Caso Relacionados

Transport of high corrosive material from the thickeners to the neutralization plant

Corrosive Material Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2015
Installation Of Pexgol Hanging Pipes In Underground Mine

Underground Mine Dewatering

Codelco Chuquicamata
Chile

 | 

2017
Installation of Pexgol Pipes for Drainage in a Vertical Ground

Vertical Dewatering

Ferrexpo Poltava Mining
Ukraine

 | 

2019
Securing the future of gold mining: Newmont Corporation chooses Pexgol for water transport

Newmont’s Water Transportation Revolution with Pexgol Pipes

Newmont Corporation
Argentina

 | 

2018
How Pexgol piping improved the fire network system infrastructure in a paint manufacturing plant.

Pexgol Piping for Fire Network System Expansion

Wall
Argentina

 | 

2023
Replacement of HDPE Pipe for Pexgol

Slurry Transportation

Tizapa Mine
Mexico

 | 

2015