Skip to content

Secondary Injection Water Plant

Installation of Pexgol Pipe in a Formation Water Treatment Plant.

Estudo de Caso Nº

96

Cliente

YPF
Argentina

|

2020

Condições de Trabalho

Maximum flow: 700m3 / h (400 m3 / h Normal) Maximum speed: 6.4 m / s (3.6m / s Normal) Temperature: 60°C / 140°F Maximum pressure: 5 kg / cm2 Normal pressure: 2 kg / cm2

Solução Pexgol

Pexgol 225 mm (8”), Class 10

Aplicação

Formation salt water with traces of hydrocarbons

Comprimento

70 m

Categorias

Installation of Pexgol Pipe in a Formation Water Treatment Plant.

The Challenge

YPF, Argentina’s national hydrocarbon exploration and production company, in its Formation Water Treatment Plant, for Secondary Injection in the La Ventana area, Vacas Muertas Oilfield, required an alternative solution to the replacement of a 25 m long pipe and 12”diameter. The formation water characteristics are high salt content (35 gr/l), with a high corrosive potential in carbon steel ducts, which require adequate internal coatings to avoid damage in less than a month of service.

Even with the proper protections, the high flow rate, and changes of direction, there is a great probability of damage in relatively short times, especially in areas close to welds.

Pexgol Solution

Together with the YPF Processing Plants department, it was proposed to carry out a test of the Pexgol pipes, as well as the electrofusion and flanged joints. The tests were carried out under the conditions and terms of a Test Protocol for 60 days. 12-inch steel pipe was replaced by 8-inch Pexgol pipe that will be subjected to the same conditions but with a higher flow velocity close to 6.5 m / s.

Installation and commissioning took only two days: one for pre-assembly and the second day for installation. In contrast, the preparation, shipment and installation of the steel pipe would require a time close to two months. The cost of the Pexgol solution represents 25% of the 8-inch diameter steel pipe.

Estudos de Caso Relacionados

Replacement of HDPE Pipe for Pexgol

Slurry Transportation

Tizapa Mine
Mexico

 | 

2015
Pexgol technology can overcome challenges in shallow well applications, offering an efficient and cost-effective solution for leading companies in the agricultural industry.

Success in Agricultural Desalination: Water Supply Challenges

BerryMex
Mexico

 | 

2019
In an engineering challenge, the Pexgol 225 mm (8”) Class 15 pipe proved to be the perfect solution for transporting tailings at the Mina Capela mining complex.

Environmental Protection and Efficiency in Tailings Management

Mina Capella - Grupo Peñoles
Mexico

 | 

2023
Reduced wear and increased durability in the sand cleaning process at KSB de México.

Improving efficiency in steel foundry with Pexgol

KSB de Mexico
Mexico

 | 

2023
Transportation of water with solids from an open cast mine

Open Cast Mine Dewatering

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2013
Pexgol’s Role in Enhancing Guaymas Protein’s Operations.

Transition to Corrosion-Free Diesel Delivery Systems

Guaymas Protein
Mexico

 | 

2023