Skip to content

Water and Sulfide Transportation

Water transportation with sulfide and cobalt particles

Estudo de Caso Nº

22

Cliente

Moa Nickel S.A. Sherritt
Cuba

|

2015

Condições de Trabalho

110°C – 1 bar.

Solução Pexgol

Pexgol 250 mm Class 12.

Aplicação

Water transportation.

Comprimento

40 m.

Categorias

Water and Sulfide Transportation

The Challenge

Moa Nickel transported water with nickel sulfide particles, this liquid formed a paste that was incrusted on the pipe walls and elbows, reducing it inside diameter. In order to repair the issue, they needed to stop the production plant, which required long maintenance time and as a consequence it decreased their productive capabilities.

Pexgol Solution

The former stainless steel pipe was replaced for a Pexgol pipe 250 mm, class 12. Even though the pipe had low thickness, it didn’t have problems such as wear nor incrustations. Likewise, due to its low roughness coefficient is lower than the titanium pipes, the head losses decreased and the pipe managed to work in a lower pressure with a greater flow.

Since the installation, the client didn’t spend on maintenance.

Estudos de Caso Relacionados

The Original Design for a Wastewater Treatment Plant included Stainless Steel Pipes, but after discovering the Superior Capabilities of Pexgol Pipes, the Entire Facility was Switched Over.

New Wastewater Treatment Plant with Pexgol Pipes

Wastewater Treatment Plant
Israel

 | 

2022
Corrosion-resistant, lightweight piping for challenging mining environment.

Pexgol Enhances Lithium Brine Well Testing Manifolds

Gaana Servicios Mineros
Argentina

 | 

2024
Installation of a Pexgol Line 200 Meters Deep at an Underground Mine

Transport of Compressed Air

Meridian Mine – Faena El Peñón
Chile

 | 

2018
Pexgol technology can overcome challenges in shallow well applications, offering an efficient and cost-effective solution for leading companies in the agricultural industry.

Success in Agricultural Desalination: Water Supply Challenges

BerryMex
Mexico

 | 

2019
Installation of 3000 Meters Of PE-X Pipe for an Underground Mine.

Drainage Lines in Underground Mine

Lundin Mining – Candelaria Norte Mine
Chile

 | 

2020
Installation of Pexgol Pipe for Transportation of Mining Tailings.

Tailings Transport with 50% solids

Golden Resource Corp. – Don David Gold Mine
Mexico

 | 

2019