Water Drainage at an Underground Mine

Water Drainage From the Inside of an Underground Mine

Estudo de Caso Nº

31

Cliente

El Peñón Yamana Gold, Meridian Mine
Chile

|

2016

Condições de Trabalho

Extreme temperatures (-5° to 38°C).

Solução Pexgol

Pexgol 160 mm Class 15 (SDR 11).

Aplicação

Water drainage.

Comprimento

600 m.

Categorias

Water Drainage From The Inside Of An Underground Mine

The Challenge

The water drainage from the inside of Meridian underground mine was processed through an HDPE 12 meter pipe that required 50 joints to be installed. The total installation time was 4 days, with no chance to minimize costs. Furthermore, the pump operated over it efficiency levels.

Pexgol Solution

A 600 meters Pexgol pipe 160 mm Class 15 was provided, in one section without joints. The Pexgol pipe was carried for 6 kilometers in 2 turns, which caused as a result 50% of time saved in the installation.

Due to the lower load losses, now the pump operates at its mayor efficiency level.

Estudos de Caso Relacionados

Installation of a Borehole with Pipe in Sections for Reduced Space.

Installation of Water Well in Reduced Space

Mekorot
Israel

 | 

2020
High-pressure water transport for the Southern Pit in a copper and zinc mine.

High-pressure fluid transport

Minera Antapaccay
Peru

 | 

2023
Transport of Muddy Water (Pome) witha High Content of Organic Load.

Transport of Muddy Water in a Palm Oil Processing Plant

La Gloria
Colombia

 | 

2020
Installation of a New Pexgol Pipeline to Provide Hot Water for a Electro-Thermal Storage System.

Hot Water Distribution for Solar Technology

Raygen
Australia

 | 

2021
Pexgol Pipe Installation for Open Pit Mine Drainage.

Efficient Open Pit Mine Drainage

BHP Escondida Mine
Chile

 | 

2022
Installation of Pexgol Pipe for Transportation of Mining Tailings.

Tailings Transport with 50% solids

Golden Resource Corp. – Don David Gold Mine
Mexico

 | 

2019