Water Drainage at an Underground Mine

Water Drainage From the Inside of an Underground Mine

Estudo de Caso Nº

31

Cliente

El Peñón Yamana Gold, Meridian Mine
Chile

|

2016

Condições de Trabalho

Extreme temperatures (-5° to 38°C).

Solução Pexgol

Pexgol 160 mm Class 15 (SDR 11).

Aplicação

Water drainage.

Comprimento

600 m.

Categorias

Water Drainage From The Inside Of An Underground Mine

The Challenge

The water drainage from the inside of Meridian underground mine was processed through an HDPE 12 meter pipe that required 50 joints to be installed. The total installation time was 4 days, with no chance to minimize costs. Furthermore, the pump operated over it efficiency levels.

Pexgol Solution

A 600 meters Pexgol pipe 160 mm Class 15 was provided, in one section without joints. The Pexgol pipe was carried for 6 kilometers in 2 turns, which caused as a result 50% of time saved in the installation.

Due to the lower load losses, now the pump operates at its mayor efficiency level.

Estudos de Caso Relacionados

Reduction of material build-up in brine and brine/acid lines

Mineral Processing – Brine Transportation

SQM,Pedro Valvidia Mine
Chile

 | 

2010
Slurry transportation with high nickel levels

Leached Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2013
The Robust & Flexible Answer to Constantly Changing Mine Surfaces.

Evolving Mine Operations with Pexgol Piping

Peña Colorada
Mexico

 | 

2023
Química del Rey replaced a corroded steel column with a Pexgol line, achieving a faster, safer, and more durable installation.

Reliable Solution for Deep Wells in Corrosive Environments

Química del Rey
Mexico

 | 

2022
Replacement Of PVC Piping for PE-X in a Industrial Heating System.

Transport of Hot Air for Advanced Agriculture

Teva Post
Israel

 | 

2022
Transformation in the logistics of formation water.

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

Aconcagua Energía
Argentina

 | 

2023