Water Transport with Low pH Level

Transport of acid water at high temperatures

Estudo de Caso Nº

2

Cliente

Moa Nickel S.A. Sherritt
Cuba

|

2010

Condições de Trabalho

Up to 65°C, 13 bars.

Solução Pexgol

Pexgol 225 mm, Class 24 (SDR 7.3).

Aplicação

Transportation of Acid Water.

Comprimento

2500 m.

Categorias

Level pH Low with Transport Water

The Challenge

Moa Nickel required to transport a big amount of overflow acid water from the sedimentation tanks to the slurry thickeners plant.

This overflow water substituted the reposition water that the slurry thickeners used.

The client debated regarding the use of a stainless steel pipe SS316L or thermoplastic flexible materials such as HDPE and polyethylene.

Pexgol Solution

At the end, Moa Nickel decided to use Pexgol pipes in long sections, instead of short ones of HDPE and polyethylene, as the best solution for the line, because this type of materials didn’t allow to work under the security standards in the allowable installation time.

The Pexgol pipe was installed in just 8 days with success. The fact that it didn’t require to create a sand bed and the high productivity for its installation in long sections, reduced to the half the installation time for this project. At the end, the client got 25% savings in comparison with the other possible materials.

Estudos de Caso Relacionados

Installation of Pexgol Pipes in a Fish Processing Plant.

Fish Oil Transport at 36°C / 96.8°F

Guaymas Protein Company
Mexico

 | 

2018
Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

Pumping Mining Effluents

AngloGold Ashanti
Brazil

 | 

2019
Installation of Pexgol Pipesf for the Drainage of an Underground Mine.

High Pressure Drain in Underground Mine

Ojos del Salado Mine – Lundin Mining
Chile

 | 

2018
Water Transportation through Shafts

Open Cast Mine Dewatering

Agnico Eagle Pinos Altos Mine
Mexico

 | 

2017
Innovation and improvement in fluid transportation in the oil and gas industry.

Streamlining Effluent Treatment with Pexgol

Pan American Energy
Argentina

 | 

2023
Streamlining Mine Dewatering and Water Transportation with Pexgol Pipes at Cerro Negro Mine.

Overcoming Installation Hurdles and Enhancing Operational Efficiency

Newmont
Argentina

 | 

2022