Well Drainage at Mining Dam

Installation of a Drainage System between a Well and a Mining Dam.

Estudo de Caso Nº

78

Cliente

CODELCO – El Teniente Mine
Chile

|

2019

Condições de Trabalho

Extreme temperatures -5° to 35°C / 25° to 95°F

Solução Pexgol

Pexgol 250 mm (10”), class 15

Aplicação

Dewatering

Comprimento

1620 m / 5314 ft

Categorias

Installation of a Drainage System between a Well and a Mining Dam.

The Challenge

The administration of the Carén reservoir, in the commune of Alhué (Chile), receives tailings from the El Teniente mine.

The western retaining wall of the reservoir needed to be widened by at least 30 meters. In order to do that a well had to be drained that was formed by leaks from the wall at its base. The extracted water had to be returned to the dam.
Also, the drainage work had to be done in just 20 days.

Pexgol Solution

The customer finally opted for Pexgol, despite the higher cost per meter, because the final cost of the installation, that only took one week, was widely offset against the installation of HDPE pipe that would have taken about a month and a half.

The advantage of Pexgol, in this solution, lies in the supply format in coils of long lengths, which made it possible to streamline its layout in the field, with no more than a dozen couplings, thus reducing assembly time.

In addition to the quick installation, technical assistance from the local team (Crosspipe Systems) was carried out with great agility and efficiency.
A total of 11 electrofusion fittings were installed.

Estudos de Caso Relacionados

The innovative solution from Pexgol for Anglo American Peru’s piping challenges.

Navigating extreme conditions with Pexgol’s PE-X pipes

Anglo American Perú
Peru

 | 

2023
Pexgol and Fresnillo: Allies in innovative piping solutions for mining.

Safety and durability: The heart of our solutions

Minera Fresnillo
Mexico

 | 

2021
Pexgol Fittings for Brine Transportation at a Brazilian Chemical Company.

High Corrosion Resistance Against Brine

Unipar Carbocloro
Brazil

 | 

2019
The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Improvement in Brine Management through Pexgol Piping

Sales de Jujuy
Argentina

 | 

2023
Transport Of Lime Slurry At 100°C

Transport of Lime Slurry

Minas de Oro Nacional, Mulatos Mine
Mexico

 | 

2015
Installation of a Drainage System in an Open Pit Mine.

Drainage System

BHP Pampa Norte – Cerro Colorado Mine
Chile

 | 

2020