Skip to content

Comprehensive Water Transportation Solution for Urgent Projects

How Pexgol Accelerated the Supply and Installation of a Critical Line.

Case Study Nº

170

Customer

Madagascar Mining
Madagascar

|

2024

Working Conditions

Temperature: 25°C / 77°F | Flow Rate: 300 m³/h | Pressure: 28 bar | Fluid Components: Sand

Pexgol Pipes

Pexgol 280 mm (10″) class 30, 24, 19 & 15

Application

River Water Transportation

Lenght

6 km

Categories

Comprehensive Water Transportation Solution for Urgent Projects

The Challenge

A leading mining operation focused on nickel and cobalt extraction and refining in Madagascar, faced a critical challenge: ensuring a reliable water supply to its pulp plant. This required building a 6-kilometer pipeline from the nearest river to the plant.
Although the project design seemed straightforward, two key challenges emerged:

  1. High Pressure Requirements: With a height difference of 160 meters and friction losses across the 6-kilometer distance, the pipeline needed to withstand pressures of up to 28 bar.
  2. Project Urgency: The plant was running out of water, meaning the project had to be executed quickly — from pipe supply to installation — with limited resources.

The Solution

Pexgol provided an ideal solution for this project by supplying 280 mm (10”) pipes in classes 30, 24, 19, and 15. These pipes were selected due to their ability to handle high pressures, flexibility, and ease of installation. Additionally, they were supplied in long coils of 100, 200, and 300 meters, which significantly reduced the number of required connections.

The fitting system used included electrofusion couplings, flared ends, and loose flanges, ensuring secure and quick connections. Pexgol’s technical support covered the entire process, from design to on-site installation, including training and tools to optimize the project’s execution.

Ambatovy evaluated alternative solutions such as steel flexible pipes with PE coatings but ruled them out due to long delivery times and the need for specialized installation tools. Pexgol proved to be the most efficient and viable solution, providing a fast, tailored response to the client’s needs.

Pexgol’s performance in this project highlights its ability to overcome technical and logistical challenges in demanding conditions.

Related Case Studies

Горячий сильвинитовый насыщенный рассол с температурой 114 °C (237 °F)

Переработка минерального сырья — установка по переработке углекислого калия

ICL group, работы на Мертвом море
Израиль

 | 

1987
Линии подачи пресс-фильтра LASTA2

Транспортировка концентрированной медной руды

Компания BHP Billiton, месторождение, Olympic Dam, Австралия
Австралия

 | 

2014
Adapting to the demands of the process: how Pexgol solves the problems of corrosion and abrasion in the extraction of palm oil.

Implementation of Pexgol Pipelines for the Transport of Muddy Water

IACSA
Colombia

 | 

2023
Installation of a Pexgol Line for the Transport of Formation Water in an Oil Company.

Replacement of Metal Pipe with PE-X for Formation Water

Enap Sipetrol Ecuador
Ecuador

 | 

2022
Монтаж труб Pexgol на установке подготовки пластовой воды.

Установка водоподготовки для вторичной закачки

YPF
Аргентина

 | 

2020
Pexgol Pipe Installation for Open Pit Mine Drainage.

High Pressure Dewatering in Open Pit Mine

Lundin Mining
Chile

 | 

2021