Optimization of Potable Water Supply for 1,600 residents

Enhanced hydraulic and structural reliability for critical community infrastructure.

Case Study Nº

188

Customer

Rincón de la Candelaria
Mexico

|

2025

Working Conditions

Temperature: Ambient | Flow rate: 50 lps (177 m³/h) | Pressure: 242 psi | Fluid composition: Groundwater

Pexgol Pipes

Pexgol 6” SDR 9

Application

Potable water transport

Lenght

630 m / 2066 ft

Categories

Optimization of Potable Water Supply for 1,600 residents

The Challenge

The Rincón de la Candelaria community, located in the municipality of Atlacomulco, State of Mexico, at 2,614 meters above sea level, relies on a pumping system to supply potable water from a groundwater source, with an operating flow rate of 50 lps (177 m³/h) and working pressure of up to 242 psi.

The existing pipeline, constructed with 6” SDR 9 HDPE 4717 pipe, presented recurring failures at the thermofusion joints.

Despite having protection accessories at the pumping station, the required pipeline route—crossing urbanized areas between houses and roads—prevented the installation of additional surge protection devices.

As a result, the pipeline was exposed to transient pressure increases caused by water hammer phenomena inherent to well operation. These overpressures compromised the structural integrity of the pipeline and caused service interruptions for approximately 1,600 residents.

Additionally, the groundwater contained minerals such as calcium, magnesium, iron, manganese, sodium, potassium, and bicarbonates, which may promote scaling and affect hydraulic performance in conventional systems.

The Solution

A total of 630 meters of 6” SDR 9 Pexgol pipe were installed, integrating into the system a flanged coupling, with the objective of ensuring greater hydraulic stability against water hammer events generated by well operation.

Thanks to its crosslinked molecular structure (PE-Xa), Pexgol provides superior resistance to transient overpressures and dynamic stresses, reducing the risk of failure compared to the previously installed HDPE pipe. This allowed improved operational reliability without modifying the existing route or incorporating additional protection devices.

The installation was carried out with limited resources and with the support of community personnel, under specialized technical supervision. Despite logistical constraints, water supply was restored in just two days, minimizing the impact on the community.

Additionally, the reduced trench depth requirement (0.60 m) allowed installation along the original route, avoiding deep excavations and additional infrastructure removal work. The result was a faster, more efficient solution with extended service life for the potable water system.

Related Case Studies

Монтаж труб Pexgol для транспортировки пластовой воды (с газом и минералами)

Газовые скважины: обработка пластовой воды

Canacol
Колумбия

 | 

2018
Guaranteeing an efficient water supply with the Pexgol piping solution in the Mendoza-San Juan Highway project.

Streamlining Water Supply in Highway Construction

Chediack / Ceosa
Argentina

 | 

2023
Транспортировки суспензии с высоким содержанием никеля

Транспортировка выщелоченной суспензии

Компания Moa Nickel S.A. Sherritt
Куба

 | 

2013
Трубы Pexgol для транспортировки сточных вод при температуре 30 °C / 86 °F в подземном руднике.

Перекачка сточных вод от горных работ

AngloGold Ashanti
Бразилия

 | 

2019
Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

Cold Water Distribution for External Cooler System

Chip Manufacturer
Israel

 | 

2022
A Case Study on the Collaborative Engineering and Strategic Implementation of the Pexgol Pipeline System for Public Safety and Efficiency

Innovation in Safety: Pexgol Piping System for LPG Supply

Rawabi City
Israel

 | 

2010