Pexgol’s Piping Solution for Regal Petroleum.

Case Study Nº

152

Customer

Regal Petroleum Corporation
Ukraine

|

2023

Working Conditions

Temperature: 15°C / 59°F | Flow: 4.2 — 8.4 m³/hour | Pressure: 17 bar | Fluid components: formation water with 20% methanol and hydrocarbons less than 1% | Additional Factors: pH 4.4, high mineralization (13.8% NaCl+KCl, 3.2% CaCl2)

Pexgol Pipes

Pexgol 110 mm, class 19

Application

Formation Water Transportation

Lenght

3,402 m / 11,159 ft

Categories

Overcoming Piping Challenges in Hydrocarbon Transportation

The Challenge

Regal Petroleum Corporation Limited, operating in Ukraine’s Poltava region, faced a significant issue with their existing carbon steel pipeline. Tasked with transporting formation water containing methanol and traces of hydrocarbons, the pipeline suffered from severe corrosion. Additionally, the requirement for underground installation with horizontal directional drilling further complicated the scenario. The project, set in 2023, demanded a durable, corrosion-resistant solution for a pipeline of 110 mm in diameter, stretching over 3,402 meters (11,159 feet) through varied underground conditions. The transportation environment involved a maximum temperature of 15°C (59°F), a fluid flow rate between 4.2 and 8.4 m³/hour, and a pressure of 17 bar. The fluid’s composition was challenging, comprising 20% methanol, less than 1% hydrocarbons and formation water with a pH of 4.4 and high mineralization.

Pexgol Solution

Pexgol presented a comprehensive solution with their PE-X pipes, designed to address the intricate needs of Regal Petroleum.
The installation utilized EF couplers and transition nipples for seamless integration with the existing steel pipeline. Pexgol’s approach emphasized fast installation, lightweight handling, and the efficient transportation of pipes in coils. The initial decoiling process faced hurdles when using a bulldozer, leading to a revised strategy of horizontal uncoiling. A trencher and the Ditch Witch JT3020 drilling equipment facilitated the underground installation, achieving a pullback speed of 0.6 meters per minute.

A key aspect of the project was the customer-specific request for pressure testing:
one 300-meter coil underwent a rigorous test, sustaining a static pressure of 24 bar for 6 hours, validating its suitability for horizontal directional drilling. This demonstrated Pexgol’s ability to meet specialized requirements and underscored their commitment to quality assurance. The successful implementation of Pexgol’s piping system provided a robust, flexible, and corrosion-resistant solution, effectively meeting the complex demands of underground hydrocarbon transportation.

Related Case Studies

Pexgol’s piping system enabled Nexa Resources to revamp their waste management process, significantly reducing environmental impact.

Enhancing Nexa Resource’s Waste Management Using Pexgol Pipes

Nexa Resources
Brazil

 | 

2023
Pexgol Pipe Installation for Open Pit Mine Drainage.

High Pressure Dewatering in Open Pit Mine

Lundin Mining
Chile

 | 

2021
Transport of acid water at high temperatures

Water Transport with Low pH Level

Moa Nickel S.A. Sherritt
Cuba

 | 

2010
Mining Effluent Transportation in Cuba.

Pexgol Optimizes Tailings Management at Sherritt’s Moa Nickel Mine

Sherritt
Cuba

 | 

2020
Pexgol’s resistance to scaling and chemicals delivers consistent operation in open-pit mining.

Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

Buena Vista del Cobre
Mexico

 | 

2024
Replacement of HDPE Pipes For Pe-X to Transport Industrial Treated Water.

Industrial Waste Water to MBR Treatment Facility

Chip Manufacturer
Israel

 | 

2021