High Pressure Dewatering in Open Pit Mine

Pexgol Pipe Installation for Open Pit Mine Drainage.

Case Study Nº

102

Customer

Lundin Mining
Chile

|

2021

Working Conditions

Flow: 720 m3/h

Pexgol Pipes

Pexgol 315 mm (12”), Class 32

Application

Open pit mine dewatering

Lenght

3240 m / 10629 ft

Categories

Pexgol Pipe Installation for Open Pit Mine Drainage.

The Challenge

Lundin Mining, in its Candelaria Tierra Amarilla mining unit, required the installation of a high-pressure dewatering line from the lower level, passing through mine banks.

Due to time problems, the mining company needed to have a pipeline where its installation would not be invasive for the mining operation and continue working in the shortest period of time possible.

Pexgol Solution

After receiving advice from the local team (Crosspipe Systems) the client decided to install 3240 meters of Pexgol 315 mm class 32 pipe for their mine dewatering system. The project consisted of 5 pumping stations, with dropouts of up to 200 meters between banks, with twin lines of Pexgol 315 mm class 32.

EF couplers, metallic reinforcement and alignment clamps were used for the projection of joints in the dropouts.

Pexgol was selected for its long-length supply format, for its ability to be unhooked from the mine benches and the possibility of providing short installation times, which facilitated assembly and commissioning.

Related Case Studies

Pvc Pipe Replacement by Pexgol

Transportation of sodium sulfide

Magnelec S.A. de C.V.
Mexico

 | 

2018
Pexgol Pipe Installation for Open Pit Mine Drainage.

Efficient Open Pit Mine Drainage

BHP Escondida Mine
Chile

 | 

2022
High Pressure Water Transport for a Gold Mine.

High Pressure Water Transport

Mansfield Mine
Argentina

 | 

2019
Pexgol Pipe Installation for the Transport of Cyanide Water.

Transport of Cyanide Water

Equinox Gold
Mexico

 | 

2022
Installation of a New Pexgol Pipeline to Provide Hot Water for a Electro-Thermal Storage System.

Hot Water Distribution for Solar Technology

Raygen
Australia

 | 

2021
Installation of Pexgol Pipe for the Transport of Abrasive Tailings.

Abrasive Tailings Transport

Pirquitas Mine
Argentina

 | 

2015