Skip to content

Slurry Transportation

Replacement of HDPE Pipe for Pexgol

Case Study Nº

36

Customer

Tizapa Mine
Mexico

|

2015

Working Conditions

Pressure 100 Psi; Flow 225 mД/h; Specific Weight 1.2 t; Solids 20-30%.

Pexgol Pipes

Pexgol 10” 250 mm, Class 15 (SDR 11).

Application

Slurry transportation.

Lenght

200 meters.

Categories

Replacement of HDPE Pipe for Pexgol

The Challenge

Tizapa Mine formerly installed an HDPE line were they used to transport slurry. This pipe suffered several failures on the joints, so did the thermo-fusions and the stub-ends as well.

They determinate that the failures were caused by small water hammers on the line.

Pexgol Solution

Due to this special circumstances, Tizapa Mine decided to install Pexgol pipes for the following reasons:

  • Supplied in long lengths coils: Of 100 meters each, reducing possible failures in the joints.
  • It high resistance to water hammers.
  • Burst pressure: 3 times higher than nominal pressure.
  • Safe joints: They don’t deform neither detach caused by a pressure surge.
  • Quick installation: Coils were uncoiled in 1.5 work hours, without any complex equipment.

Related Case Studies

The Original Design for a Wastewater Treatment Plant included Stainless Steel Pipes, but after discovering the Superior Capabilities of Pexgol Pipes, the Entire Facility was Switched Over.

New Wastewater Treatment Plant with Pexgol Pipes

Wastewater Treatment Plant
Israel

 | 

2022
Replacement of Carbon Steel Pipes with Pexgol for the Transportation of Natural Gas.

Natural Gas Transportation with Pexgol

YPF
Argentina

 | 

2022
Explore how Pexgol pipe replacement addressed the corrosion issue in Gordon Pool’s saltwater delivery system, ensuring efficient operation.

From Steel to Pexgol: A Plumbing Upgrade for Tel Aviv’s Gordon Pool

Gordon Pool
Israel

 | 

2023
Installation of Pexgol Pipe in a Formation Water Treatment Plant.

Secondary Injection Water Plant

YPF
Argentina

 | 

2020
Pexgol’s chemical resistance and flexibility outperform HDPE in demanding leach pad operations.

Greater Efficiency and Safety in Leaching with Pexgol Pipes

Barrick Gold Corp.
Argentina

 | 

2025
Transportation of brackish water to the main pumping station

Water Lines – Harsh Conditions

Dead Sea Works
Israel

 | 

1993