Skip to content

Safe Installation of a 355 mm Mine DewateringLine

A flexible and durable solution designed to adapt to pit benches, operate outdoors, and minimize connection work in difficult-to-access areas.

Caso de Estudio Nº

197

Cliente

MMG
Perú

|

2024

Condiciones Operativas:

Temperature: 27°C / 80.6° F | Pressure: 25 bar / 363 psi pumping pressure | Fluid: Mine water, 5% solids, pH 6

Tuberías Utilizadas:

Pexgol 355 mm

Uso:

Mine dewatering

Largo:

870 m / 2,854 ft

Categorías:

Safe Installation of a 355 mm Mine DewateringLine

The Challenge

Las Bambas needed to install a dewatering line capable of transporting mine water at a pumping pressure of 25 bar in an environment characterized by steep slopes, benches, and mining conditions.

The pipeline had to adapt to the irregular terrain geometry and operate safely outdoors, exposed to solar radiation and low temperatures, without needing to be buried.

Another critical requirement was to minimize installation work on the pit slope. Conventional steel or HDPE pipes are typically supplied in sections approximately 12 or 14 m long, which would have required a greater number of field connections. This meant additional labor, longer installation times, and greater exposure of personnel to high-risk work. In addition, every additional joint represented a potential failure point in a location subject to high operating pressures.

The Solution

A 355 mm Pexgol pipe was selected and supplied in coils with continuous sections of up to 90 m.

The coiled format significantly reduced the number of connections required along the 870 m installation. Compared with the shorter sections commonly used in steel or HDPE systems, this solution reduced labor requirements and minimized potential pipeline failure points.

The inherent flexibility of Pexgol pipe allowed the line to follow changes in direction and adapt to the irregular terrain, making it easier to install along the pit benches without burying the pipeline.

Specialized equipment was used for the installation, including a vertical pay-offvunit due to the size and weight of the coils. Connections were completed using electrofusion couplings, stub ends, and flanges installed at the pipe ends. The use of long sections also made it possible to complete numerous joints away from the pit slope, reducing the time personnel spent in difficult-to-access areas and improving overall installation safety.

As a result, Las Bambas obtained a flexible, high-pressure-resistant pipeline suitable for open-air mine operation, with fewer joints, faster installation, and reduced personnel exposure to high-risk work.

Casos de Estudio Relacionados

Instalación de una Nueva Tubería Pexgol para Proveer Agua Caliente a un Sistema de Almacenamiento Electrotérmico.

Distribución de Agua Caliente para Tecnología Solar

Raygen
Australia

 | 

2021
Transporte de Aguas Grises para Reciclaje

Transporte de Agua Recuperada

Coeur Mexicana S.A. de C.V. Palmarejo
México

 | 

2017
Accesorios Pexgol para el Transporte de Salmuera en una Empresa Química Brasileña.

Alta Resistencia a la Corrosión para Transporte de Salmuera

Unipar Carbocloro
Brasil

 | 

2019
Minas Argentinas reemplaza HDPE por Pexgol en su proyecto de lixiviación secundaria.

Riego eficiente y seguro en lixiviación secundaria con Pexgol

Minas Argentinas S.A.
Argentina

 | 

2025
Drenaje de Agua desde el Interior de una Mina Subterránea

Drenaje de Agua en Mina Subterránea

El Peñón Yamana Gold, Meridian Mine
Chile

 | 

2016
Transporte de Agua desde una Mina Subterránea en Condiciones de Alta Presión

Desagüe de Mina Subterránea

Antofagasta Minerals, Michilla Mine
Chile

 | 

2011