Skip to content

Safe Installation of a 355 mm Mine DewateringLine

A flexible and durable solution designed to adapt to pit benches, operate outdoors, and minimize connection work in difficult-to-access areas.

Estudo de Caso Nº

197

Cliente

MMG
Perú

|

2024

Condições de Trabalho

Temperature: 27°C / 80.6° F | Pressure: 25 bar / 363 psi pumping pressure | Fluid: Mine water, 5% solids, pH 6

Solução Pexgol

Pexgol 355 mm

Aplicação

Mine dewatering

Comprimento

870 m / 2,854 ft

Categorias

Safe Installation of a 355 mm Mine DewateringLine

The Challenge

Las Bambas needed to install a dewatering line capable of transporting mine water at a pumping pressure of 25 bar in an environment characterized by steep slopes, benches, and mining conditions.

The pipeline had to adapt to the irregular terrain geometry and operate safely outdoors, exposed to solar radiation and low temperatures, without needing to be buried.

Another critical requirement was to minimize installation work on the pit slope. Conventional steel or HDPE pipes are typically supplied in sections approximately 12 or 14 m long, which would have required a greater number of field connections. This meant additional labor, longer installation times, and greater exposure of personnel to high-risk work. In addition, every additional joint represented a potential failure point in a location subject to high operating pressures.

The Solution

A 355 mm Pexgol pipe was selected and supplied in coils with continuous sections of up to 90 m.

The coiled format significantly reduced the number of connections required along the 870 m installation. Compared with the shorter sections commonly used in steel or HDPE systems, this solution reduced labor requirements and minimized potential pipeline failure points.

The inherent flexibility of Pexgol pipe allowed the line to follow changes in direction and adapt to the irregular terrain, making it easier to install along the pit benches without burying the pipeline.

Specialized equipment was used for the installation, including a vertical pay-offvunit due to the size and weight of the coils. Connections were completed using electrofusion couplings, stub ends, and flanges installed at the pipe ends. The use of long sections also made it possible to complete numerous joints away from the pit slope, reducing the time personnel spent in difficult-to-access areas and improving overall installation safety.

As a result, Las Bambas obtained a flexible, high-pressure-resistant pipeline suitable for open-air mine operation, with fewer joints, faster installation, and reduced personnel exposure to high-risk work.

Estudos de Caso Relacionados

Replacing Steel for PE-X Pipes to Transported Processed Water.

Replacement of Steel Pipes for PE-X

Rosebel Gold Mines – IamGold
Suriname

 | 

2020
Record-time intervention that avoided operational losses in a dehydration plant.

Critical Pipeline Replacement in Dehydration Plant with Operational Continuity

Petróleos Sudamericanos
Argentina

 | 

2025
The impact of Pexgol piping on pump performance improvement and maintenance cost reduction at Sales de Jujuy.

Improvement in Brine Management through Pexgol Piping

Sales de Jujuy
Argentina

 | 

2023
Test Of Pexgol Pipes Vs Hdpe Pipes For Brine Transportation

Test: Pexgol vs HDPE for Brine Transportation

YBL
Bolivia

 | 

2017
Sewage Water Transportation with 300 PPM Hydrogen Peroxide

Sewage Water Transportation

BorsodChem
Hungary

 | 

2011
Test Installation for Transporting Silica Sand.

Transport of Silica Arena: HDPE vs Pexgol

Covia Corp
Mexico

 | 

2019