Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

600 Meters Installed in a Day: Pexgol Delivers for Kiewit in Power Project.

Estudo de Caso Nº

177

Cliente

Kimex
Mexico

|

2025

Condições de Trabalho

Temperature: 16°C – 31°C (Ambient) | Pressure: 3 bar | Flow Rate: 115 m³/hr | Fluid: Boiler feedwater

Solução Pexgol

Pexgol 4″ SDR 11

Aplicação

Water conveyance for power plant commissioning

Comprimento

600 m / 1968 ft

Categorias

Pexgol Ensures Water Supply at Mexican Combined-Cycle Power Plant

The Challenge

Kiewit Corp., through its subsidiary Kimex SA de CV, faced a critical requirement during the construction of the CCC Tuxpan Phase 1 combined-cycle power plant in Mexico. To initiate testing and commissioning, the new facility needed to be supplied with boiler feedwater—a fluid requiring high purity and specific properties.

The challenge: the site under construction lacked an operational water treatment system, and any solution had to be immediate, highly reliable, and compatible with Kiewit’s rigorous safety protocols. Additionally, the piping had to withstand conditions typical of an active construction environment.

The Solution

Pexgol proved to be the ideal choice. In just one day, 600 meters of 4” SDR 11 Pexgol pipe were installed using only standard on-site machinery and tools, with no need for specialized equipment. The very next day, the system was operational, enabling the project team to start equipment testing without delay.

The line transported boiler feedwater at 3 bar of pressure and a flow rate of 115 m³/h, operating smoothly within the site’s ambient temperature range of 16°C to 31°C.

A key success factor was Kiewit’s validation of internal safety protocols. Although using coiled piping was new to their team, the installation was incident-free, demonstrating Pexgol’s safety and reliability even in demanding construction environments.

Key Benefits:

  • Rapid installation without specialized equipment
  • Flexible and impact-resistant material, ideal for active worksites
  • Excellent chemical and corrosion resistance
  • Lightweight and easy to handle
  • Full compliance with international safety protocols

Fittings Used:

  • Flared End / Stub End
  • Loose Flange
  • Fixpoint Bridge

Estudos de Caso Relacionados

Replacing HDPE pipes with Pexgol allowed Vale to simplify operations, eliminate auxiliary equipment, and achieve a permanent installation under extreme conditions.

Comprehensive Redesign of the PumpingSystem with Pexgol at the Sossego Mine

Vale
Brazil

 | 

2024
The mine was facing scaling issues with their existing HDPE pipes, which required replacement every two weeks. The introduction of Pexgol pipes drastically reduced scaling.

Pexgol: Significant Pipe Wall Scale Reduction

Copper Mine
USA

 | 

2022
Installation of 1000 Meters of PE-X Pipe for an Underground Mine.

Mining Drainage Lines

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019
Mining Effluent Transportation in Cuba.

Pexgol Optimizes Tailings Management at Sherritt’s Moa Nickel Mine

Sherritt
Cuba

 | 

2020
Installation of Pexgol Pipes for Drainage of an Underground Mine

Vertical Drain in Underground Mine

Meridian Mine - Faena El Peñón
Chile

 | 

2018
Coarse NACL (SALT) Dredging Tailing

Slurry Lines – Abrasive Dredged Material

ICL group, Dead Sea Works
Israel

 | 

1992