Skip to content

Durable Solution Against Abrasion in Production Facilities: Pexgol at YPF

Performance evaluation of Pexgol lining under extreme service conditions.

Estudo de Caso Nº

175

Cliente

YPF
Argentina

|

2018

Condições de Trabalho

Temperature: 75°C / 167°F | Pressure: 8 kg/cm² | Fluid components: Hydrocarbons and produced water from wells (with sand presence)

Solução Pexgol

Pex-lined elbow

Aplicação

Pex-lined reducing elbow in oil production facility – Abrasion

Comprimento

N/A

Categorias

Durable Solution Against Abrasion in Production Facilities: Pexgol at YPF

The Challenge

YPF, Argentina’s leading oil and gas exploration and production company, was facing recurring failures in various components of the Aguada Toledo 3 Production Facility (Bat-AT3), particularly in the pump discharge circuit.
The failures were identified in flow restriction areas such as pump discharge reducers, flow control valves, and orifice plates. These components were internally coated with epoxy layers ranging from 250 to 650 µm in thickness.

YPF’s internal studies identified two main deterioration mechanisms:

  • Flow-assisted corrosion, considered the most likely cause.
  • Localized corrosion due to occluded cells, caused by partial detachment of the internal epoxy lining.

Material loss was estimated at 7 to 9 mm of wall thickness per year under continuous operation, with damage concentrated in reducers and elbows. Considering that the 6” circuit and the 6” to 3” reducing elbow had a wall thickness of 7.11 mm (SCH 40 steel pipe), these failures posed a serious risk to system safety and operational continuity.

The Solution

To mitigate the issue, YPF proposed testing a carbon steel component internally lined with Pexgol to assess its performance under real operating conditions. A 6” x 3” reducing elbow connected to the discharge of one of the pumps was selected for this trial.

The component was manufactured and inspected at Golan’s facility, where the internal Pexgol lining was applied. Once installed and put into operation, the elbow remained in service for 7 years without damage, despite the severe operating conditions.

The implementation of the Pexgol lining proved to be a highly effective solution, eliminating previous failures and significantly extending the system’s service life—without costly maintenance or unplanned shutdowns. This case reinforces Pexgol’s reliability in critical applications where corrosion and abrasion are ongoing challenges.

Estudos de Caso Relacionados

Installation of Pexgol Pipes for Drainage of an Underground Mine

Vertical Drain in Underground Mine

Meridian Mine - Faena El Peñón
Chile

 | 

2018
Pexgol Pipe for the Transport of Fluorosilicic Acid.

Fluorosilicic Acid Transport

Phosphate Mine – ICL Rotem
Israel

 | 

1995
Delivering Durability and Flexibility for a Sustainable Approach to Space Access.

Pioneering Space Launches with Ground-breaking Piping Solutions

SpinLaunch
USA

 | 

2021
Bridging the Gap between Durability and Functionality in Harsh Processing Environments.

Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport

Syncrude
Canada

 | 

2022
Replacement of Carbon Steel Pipes by Pexgol for Fire Fighting Network.

Water Transport for Fire Network

Profertil
Argentina

 | 

2022
Water line feed from wells to mine

Water Lines – High Pressure Water Feed Lines

Yamana Gold, Meridian Mine
Chile

 | 

2012