Hot Water Distribution for Solar Technology

Installation of a New Pexgol Pipeline to Provide Hot Water for a Electro-Thermal Storage System.

Estudo de Caso Nº

114

Cliente

Raygen
Australia

|

2021

Condições de Trabalho

Pressure: 4 bars | Temperature: up to 90°C / 194°F

Solução Pexgol

Pexgol 200 (8″), Class 12

Aplicação

Hot water distribution

Comprimento

2160 m / 7086 ft

Categorias

Installation of a New Pexgol Pipeline to Provide Hot Water for a Electro-Thermal Storage System.

The Challenge

RayGen is an Australian technology company with world-leading breakthroughs in solar power technology and renewable energy storage.

They required to provide cooling water to their concentrated solar towers. Then the water needed to return from the towers at 90°C to the thermal storage.

Pexgol Solution

The client decided to install a Pexgol system (pipe and fittings) for it’s operation, after considering the following benefits:

  • Corrosion resistance at elevated temperature without the need for coatings (compared to metallic piping).
  • Ease of installation due to long coil lengths reducing welding/connections and flexibility (compared to metallic and other rigid 6-12 m pipe lengths).
  • Low thermal expansion forces allowing direct burying without the need for extra expansion allowance (compared to metallic piping) Pexgol natural bending radius – Using the natural bending capabilities allowed reducing connections, parts and pressure drop.

The pipes were installed under ground without special pipe protection and were insulated using PIR foam sprayed directly around the pipes, after pressure testing. Then backfilled directly on top.
Special Reinforced EF Couplers Series 2 (up to 90ºC) were welded.

Estudos de Caso Relacionados

Replacement Of PVC Piping for PE-X in a Industrial Heating System.

Transport of Hot Air for Advanced Agriculture

Teva Post
Israel

 | 

2022
Test Of Pexgol Pipes Vs Hdpe Pipes For Brine Transportation

Test: Pexgol vs HDPE for Brine Transportation

YBL
Bolivia

 | 

2017
850 Meters of Pipe Replaced in Less Than 24 Hours, Without Affecting Residents.

Goodbye Asbestos: Pexgol Modernizes Thermal Water Network

Raquet Club Lake Chapala
Mexico

 | 

2024
Lasta2 Filter Press Feed Lines

Concentrated Copper Transportation

BHP Billiton, Olympic Dam, Australia
Australia

 | 

2014
Reducing maintenance and increasing safety in hydraulic backfill operations.

Pexgol Simplifies Slurry Transportation at Buriticá Mine

Zijin - Continental Gold
Colombia

 | 

2023
Groundwater Transportation With Ph Low Levels

Groundwater Transportation

Grupo México, Buena Vista del Cobre Mine
Mexico

 | 

2015