Scaling Up Efficiency: District Energy at Penn State Harrisburg

A Two-Phase Installation for High-Temperature Hot Water Supply & Return.

Estudo de Caso Nº

174

Cliente

Penn State University – Harrisburg
USA

|

2021

Condições de Trabalho

Temperature: 98°C / 210°F | Pressure: 130 psi

Solução Pexgol

Pexgol 9″ & 14″

Aplicação

District Energy Network

Comprimento

Significant

Categorias

Scaling Up Efficiency: District Energy at Penn State Harrisburg

The Challenge

Penn State University Harrisburg required a reliable and efficient solution for its High-Temperature Hot Water Supply & Return (HT-HWS&R) system. The university needed a durable piping system capable of withstanding continuous high temperatures of 210°F at 130 psi while ensuring long-term performance with minimal maintenance. The solution had to be implemented underground, with direct burial, making resistance to environmental and operational stress a key requirement.

The project was executed in two phases, with Phase 1 completed in 2021 and an expansion (Phase 2) successfully implemented in 2023. With the growing infrastructure needs of the campus, further installations are anticipated in the future.

The Solution

For Phase 1 of the project, the university selected Pexgol 225 mm (9” Nom.) SDR 6 piping. The pipes were supplied in coils, allowing for efficient installation with minimal joints. The system was buried directly, with field-applied closed-cell spray foam insulation to ensure energy efficiency and temperature retention. Since its commissioning in 2021, the system has provided reliable service.

Following the success of Phase 1, Phase 2 was initiated in 2023, incorporating larger Pexgol 355mm (14” Nom.) and 225mm (9” Nom.) SDR 6 pipes. Like the first phase, the pipes were delivered in coils for direct burial, reducing installation time and costs while maintaining the same high-temperature and pressure resistance. The field-applied spray foam insulation continued to enhance thermal efficiency.

Penn State Harrisburg continues to expand its district energy network with Pexgol solutions, with additional phases expected in the near future. This project showcases Pexgol’s ability to meet demanding, long-term district heating requirements with efficiency, reliability, and cost-effectiveness.

Estudos de Caso Relacionados

Installation of a drainage system between a well and a mining dam.

Drinking Water on Sloping Terrain

AquaMag
Colombia

 | 

2019

Categories:

Installation of Pexgol Pipe to Transport Fiber Optic Cables.

Fiber Optic Cables Through a Vertical Shaft

Sinohydro
Israel

 | 

2021
Bridging the Gap between Durability and Functionality in Harsh Processing Environments.

Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport

Syncrude
Canada

 | 

2022
Pvc Pipe Replacement by Pexgol

Transportation of sodium sulfide

Magnelec S.A. de C.V.
Mexico

 | 

2018
Case Study: Pexgol’s Solution at the Palm Oil Plant.

Efficiency and Durability in Handling Muddy Water

Industrial Aceitera del Casanare
Colombia

 | 

2023
Transport of acid water at high temperatures

Water Transport with Low pH Level

Moa Nickel S.A. Sherritt
Cuba

 | 

2010