Mine Dewatering – High Pressure Conditions

Water line feed from wells to mine

Estudo de Caso Nº

6

Cliente

Antofagasta Minerals, Michilla Mine
Chile

|

2011

Condições de Trabalho

High pressure (over 24 bar).

Solução Pexgol

Pexgol 160×27, Class 30.

Aplicação

Dewatering.

Comprimento

700 meters.

Categorias

Mine Dewatering – High Pressure Conditions

The Challenge

Antofagasta Minerals faced constant water accumulation at the bottom of the mine, it was interfering with the extraction of the minerals. In addition, the mine operators faced:

  • High pressure (more than 24 bars) – resulting from the vertical height differences, which required a pipe that could withstand the pressure and be easily installed.
  • Pipe clogging in HDPE pipes – caused by scale formation on the pipe walls due to the presence of various salts, such as chlorides and sulfates, in varying concentrations in the water.
  • Long installation time – and the need to reduce it by installing a flexible, long pipeline with less connections.

Pexgol Solution

The installation of a Pexgol’s flexible pipe, which was produced and transported in coils, reducing both installation time as well as the number of joints. Since installation in early 2011, it has been working with no sign of clogging.

The client is fully satisfied with the pipe’s robust performance, including its quick, easy installation and ability to withstand pressures of higher than 24 bars.

Since Pexgol’s pipes require less maintenance than PE pipes and eliminate previous frequent failures, it will be used for many additional applications at the mine.

Estudos de Caso Relacionados

The transition to the Pexgol piping system allowed Paladini to ensure a smooth and efficient wastewater transport process for their agricultural irrigation.

Pexgol Pipes for Efficient Wastewater Transport

Paladini
Argentina

 | 

2022
Bridging the Gap between Durability and Functionality in Harsh Processing Environments.

Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport

Syncrude
Canada

 | 

2022
Transportation of water in more than 150 mining crossroads

Water Transport on Crossroads

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2012
Reduced wear and increased durability in the sand cleaning process at KSB de México.

Improving efficiency in steel foundry with Pexgol

KSB de Mexico
Mexico

 | 

2023
Vertical Mobile Pexgol Installation on the Rocks for Mine Dewatering.

Mine Dewatering at Low Temperature

Ferrexpo Yeristovo Mining
Ukraine

 | 

2019
Dry Gas Line for Pump Activation.

Dry Gas Transportation

ExxonMobil
Argentina

 | 

2020