Water Drainage at an Open-Cast Mine

Water Drainage in Harsh Ground

Estudo de Caso Nº

32

Cliente

Timmins Gold Corp Group, Molimentales del Noroeste Mine
Mexico

|

2016

Condições de Trabalho

Solar exposure, 14 bars.

Solução Pexgol

Pexgol 225 mm, Class 15 (SDR 11).

Aplicação

Water drainage.

Comprimento

200 m.

Categorias

Water Drainage In Harsh Ground

The Challenge

At “Molimentales” Mine in order to continue with their open-cast mining operations, it was necessary to drainage water from some sections in the ground. Formerly, the mine used an HDPE pipe of 12 meter sections, but they had constant issues due to leaks in the joints.

Pexgol Solution

A Pexgol pipe was provided, in 100 meters sections, in order to have less joints and thereby less leak risks.

Furthermore, the installation was fast and simple due to the lack of welds, and the pipes were dragged with the equipment that the mine already had available.

Estudos de Caso Relacionados

High Pressure Water Transport for a Gold Mine.

High Pressure Water Transport

Mansfield Mine
Argentina

 | 

2019
Installation of Pexgol Pipe in a Formation Water Treatment Plant.

Secondary Injection Water Plant

YPF
Argentina

 | 

2020
Acid liquor line with high levels of abrasion and sedimentation

Abrasive Liquid Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2014
Installation of a New Pexgol Pipeline to Provide Cold Water for a External Chiller System.

Cold Water Distribution for External Cooler System

Chip Manufacturer
Israel

 | 

2022
Pexgol Pipe Installation for the Transport of Water with Solids (Feathers, Bones, Viscera, Etc.)

Transportation of Water with Solids

Kofanor
Mexico

 | 

2022
Transforming water transportation with Pexgol technology

Pexgol’s Solution for CFE: A Leap in Durability and Efficiency

Comisión Federal de Electricidad
Mexico

 | 

2023