Water Transport Between Dams

Installation of a Drainage System between Dams in a Copper Mine.

Estudo de Caso Nº

77

Cliente

CODELCO – El Teniente Mine
Chile

|

2019

Condições de Trabalho

Extreme temperatures -10° to 40°C / 14° to 104°F

Solução Pexgol

Pexgol 160 mm (6”), class 15

Aplicação

Dewatering

Comprimento

5600 m / 18372.7 ft

Categorias

Installation of a Drainage System between Dams in a Copper Mine.

The Challenge

Cooperación del Cobre de Chile (CODELCO) required transporting water from the Barahona dam to a specific sector of the Caletones smelter, located south of the dam. The line was due to be installed in less than 10 weeks.

The distance of the route, in addition to other works being carried out on site and the vehicular flow, made it critical that the pipeline needed to be installed in the shortest time possible.

Pexgol Solution

The client made an economic evaluation, considering the installation time of the HDPE versus PE-X pipes from Pexgol. Pexgol was finally chosen.

The delivery format in coil of long lengths, allowed the totality of meters to be delivered in only 10 coils.
Installation was exceptionally fast. The uncoiling allowed up to 6 drums per day to be released, the sections to be located in their final location and subsequently joined with the relevant couplings, within 6 days.

As for the accessories, 9 electrofusion couplings were used.
The final experience was very satisfying.

Estudos de Caso Relacionados

Case Study: Pexgol’s Solution at the Palm Oil Plant.

Efficiency and Durability in Handling Muddy Water

Industrial Aceitera del Casanare
Colombia

 | 

2023
Installation of Pexgol Pipe for Transportation of Mining Tailings.

Tailings Transport with 50% solids

Golden Resource Corp. – Don David Gold Mine
Mexico

 | 

2019
Transportation of River Water in Rough Terrain

Water Transport in Complex Terrain

Southern Copper Corporation
Peru

 | 

2019
Transport of acid slurry at high temperatures

Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2012
The transition to the Pexgol piping system allowed Paladini to ensure a smooth and efficient wastewater transport process for their agricultural irrigation.

Pexgol Pipes for Efficient Wastewater Transport

Paladini
Argentina

 | 

2022
Transportation of mixed liquid and corrosive vapor (H2S) from the dehumidifiers

Mineral Processing Corrosive Liquid & Vapor

Moa Nickel S.A. Sherritt
Cuba

 | 

2011