Condições de Trabalho

Flow: 50 m3/h | Temperature: 80°C / 176°F

Solução Pexgol

Pexgol 110 mm (4″), class 15

Aplicação

Muddy water transport

Comprimento

200 m / 656 ft

Categorias

Efficient Choice: PE-X Pipe for the Palm Industry

The Challenge

The agroindustrial Colombian company Extractora Monterrey S A S is dedicated to the cultivation and processing of palm fruit, for the extraction of crude oil, palm kernel oil and palm kernel cake. It required the installation of a new line to transport muddy water to the oxidation ponds. From the Florentine passing the main road and the plantation, the excavation and installation of the pipe would be carried out in the crop, between palm trees without causing damage to the plants and the irrigation pipe.

Pexgol Solution

In this case, PE-X pipes were chosen because they are cheaper compared to the installation of stainless steel pipes.

Another factor that influenced the decision to use PE-X pipes was its ease of installation. The installation process was quick and easy, allowing the 200 meters of pipe to be laid in just 4 hours, using only two 15/16 wrenches, a level and a GP mechanical union.

In addition, PE-X pipes have fewer joints, which reduces the risk of leaks and therefore increases efficiency in transporting palm oil.

Finally, the recommendation of another client who had used PE-X pipes in other projects with good results also influenced the decision to use this type of pipe in the installation.

In summary, the choice of PE-X pipes in the transport of slurry water is due to its lower cost compared to stainless steel pipes, its ease of installation, fewer joints, recommendation from other clients and the speed of delivery. placement, which reduced the time and number of personnel required for installation.

Estudos de Caso Relacionados

Installation of a Drainage System between Dams in a Copper Mine.

Water Transport Between Dams

CODELCO – El Teniente Mine
Chile

 | 

2019
Mining Effluent Transportation in Cuba.

Pexgol Optimizes Tailings Management at Sherritt’s Moa Nickel Mine

Sherritt
Cuba

 | 

2020
Transport of Concentrated Alcohol to 86% for the Production of Rum and Brandy

Transportation of Alcohol for the Production of Rum and Brandy

Cuba Ron
Cuba

 | 

2016
Pexgol helped Profertil to overcome the corrosion challenge in its fire protection network.

From carbon steel to Pexgol: A victory against corrosion

Profertil
Argentina

 | 

2021
Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Hot & Abrasive Potash Brine Processing

Fertilizer Company
Canada

 | 

2017
High-pressure water transport for the Southern Pit in a copper and zinc mine.

High-pressure fluid transport

Minera Antapaccay
Peru

 | 

2023