Efficient Choice: PE-X Pipe for the Palm Industry

Pexgol pipe was selected for the Assembly of a Muddy Water Transport Line for a Palm Oil Processing Company.

Estudo de Caso Nº

120

Cliente

Extractora Monterrey
Colombia

|

2023

Condições de Trabalho

Flow: 50 m3/h | Temperature: 80°C / 176°F

Solução Pexgol

Pexgol 110 mm (4″), class 15

Aplicação

Muddy water transport

Comprimento

200 m / 656 ft

Categorias

Efficient Choice: PE-X Pipe for the Palm Industry

The Challenge

The agroindustrial Colombian company Extractora Monterrey S A S is dedicated to the cultivation and processing of palm fruit, for the extraction of crude oil, palm kernel oil and palm kernel cake. It required the installation of a new line to transport muddy water to the oxidation ponds. From the Florentine passing the main road and the plantation, the excavation and installation of the pipe would be carried out in the crop, between palm trees without causing damage to the plants and the irrigation pipe.

Pexgol Solution

In this case, PE-X pipes were chosen because they are cheaper compared to the installation of stainless steel pipes.

Another factor that influenced the decision to use PE-X pipes was its ease of installation. The installation process was quick and easy, allowing the 200 meters of pipe to be laid in just 4 hours, using only two 15/16 wrenches, a level and a GP mechanical union.

In addition, PE-X pipes have fewer joints, which reduces the risk of leaks and therefore increases efficiency in transporting palm oil.

Finally, the recommendation of another client who had used PE-X pipes in other projects with good results also influenced the decision to use this type of pipe in the installation.

In summary, the choice of PE-X pipes in the transport of slurry water is due to its lower cost compared to stainless steel pipes, its ease of installation, fewer joints, recommendation from other clients and the speed of delivery. placement, which reduced the time and number of personnel required for installation.

Estudos de Caso Relacionados

Streamlining Mine Dewatering and Water Transportation with Pexgol Pipes at Cerro Negro Mine.

Overcoming Installation Hurdles and Enhancing Operational Efficiency

Newmont
Argentina

 | 

2022
Changing carbon steel for efficiency: Pexgol PE-X pipes in Aconcagua Energía

Elevating Efficiency in Hydrocarbon Exploitation

Aconcagua Energía
Argentina

 | 

2023
Transportation of water with solids from an open cast mine

Open Cast Mine Dewatering

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2013
A Two-Phase Installation for High-Temperature Hot Water Supply & Return.

Scaling Up Efficiency: District Energy at Penn State Harrisburg

Penn State University - Harrisburg
USA

 | 

2021
Acid liquor line with high levels of abrasion and sedimentation

Abrasive Liquid Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2014
Replacement of HDPE Pipe for Pexgol

Slurry Transportation

Tizapa Mine
Mexico

 | 

2015