Alumina Plant: Ore Slurry Transportation

Transportation of Bauxite Ore Slurry at 95°C / 203°F

Estudo de Caso Nº

52

Cliente

Urals Alumina Plant – Rusal
Russia

|

2013

Condições de Trabalho

High temperature

Solução Pexgol

Pexgol 160 mm Class 15

Aplicação

Slurry Transportation

Comprimento

20 m

Categorias

Transportation of Bauxite Ore Slurry at 95°C / 203°F

The Challenge

At Urals Alumina Plant, they required to renovate their carbon steel pipes where they transport bauxite ore slurry at 95°C / 203°F. Every year these lines were suffering from sedimentation problems and it was necessary to clean them every three months, involving man power and high costs.

Pexgol Solution

The client decided to replace the carbon steel pipes with Pexgol pipes. Thanks to it smooth inner surface, sedimentation is not a problem and as a consequence requires less maintenance, lowering also costs.

The Pexgol pipes have been checked annually and even after 4,5 years of exploitation, the pipes have shown positive results. They don’t have to clean the pipes any more.

Estudos de Caso Relacionados

Pipe installation on a mountain

Meltdown Water Transport

Codelco Andina, TADA 1-2 Project
Chile

 | 

2013
Successful outcome in pilot test for SCT Discharge Line with Pexgol.

Advanced piping solutions for handlingscaling fluids

Barrick Gold
Dominican Republic

 | 

2023
Substitution of a Steel Spool for PE-X Coated for Pumping Formation Water.

Replacement of a Steel Spool with Pexgol

Enap Sipetrol
Ecuador

 | 

2021
Pexgol Transforms Tailings Transportation at Minera San Julián.

Minera San Julián Adopts Pexgol to Improve Water Management

Fresnillo plc
Mexico

 | 

2024
High Pressure Water Transport for a Gold Mine.

High Pressure Water Transport

Mansfield Mine
Argentina

 | 

2019
Transformation in the logistics of formation water.

Aconcagua Energía Implements Pexgol Solutions for Efficiency and Savings

Aconcagua Energía
Argentina

 | 

2023