Skip to content

Fish Discharge Lines

Installation of Pexgol Pipes to Transport Fish.

Estudo de Caso Nº

71

Cliente

TASA
Peru

|

2018

Condições de Trabalho

Extreme temperatures 5° to 21°C / 41° to 69.8°F

Solução Pexgol

Pexgol 355 mm (14”), class 10

Aplicação

Fish transport

Comprimento

2100 m / 6900 ft

Categorias

Installation of Pexgol Pipes to Transport Fish.

The Challenge

Tecnológica de Alimentos S.A. (TASA) required to transport Anchovy fish that measured between 12 and 15 cm from their vessels to the processing plant.

The fish was transported using HDPE pipes. The fish lost it mass due to rubbing against the walls of the pipes. These pipes were joined by thermofusion, which caused an internal burr (protruding portion of material) in the joints and increased damage to the fish. For this reason 450 mm HDPE pipes and a large amount of water must be used to transport the fish. The latter caused a considerable increase in the costs of water treatment.

Pexgol Solution

The client decided to replace its HDPE pipes and install 4 Pexgol lines for fish unloading in 3 plants of the company, with a length of 700 meters each and a diameter of 355 mm (14”) class 10. In the installation, concrete pieces were put on the pipe in order to make sure it doesn’t float on the sea.

Among the main advantages that were verified in this application were:

  • Smooth internal surface: Decreased mass loss, which results in the fish practically intact at the exit of the discharge, and therefore generates a better quality final product.
  • Lower costs for water treatment: It was possible to lower HDPE pipes of 450 mm PN 10 to Pexgol 355 mm (14”) class 10 pipes. Since it is a less rough pipe material, it allows the fish to be transported with less water, reducing more than 20% the cubic meters of water per linear meter.
  • Electrofusion unions: 178 unions were made that did not leave any type of internal burr (and therefore generate less damage to the fish).

Estudos de Caso Relacionados

Dewatering without Supports

Open Cast Mine Dewatering

El Volcan Mine Arcelor Mittal
Mexico

 | 

2017
Installation of Pexgol pipes for the transport of formation water (gas and minerals)

Gas Wells: Formation Water Treatment

Canacol
Colombia

 | 

2018
Installation Of Pexgol Hanging Pipes In Underground Mine

Underground Mine Dewatering

Codelco Chuquicamata
Chile

 | 

2017
Lasta2 Filter Press Feed Lines

Concentrated Copper Transportation

BHP Billiton, Olympic Dam, Australia
Australia

 | 

2014
Transportation of water with solids from an open cast mine

Open Cast Mine Dewatering

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2013
Groundwater Transportation With Ph Low Levels

Groundwater Transportation

Grupo México, Buena Vista del Cobre Mine
Mexico

 | 

2015