Replacement of Corroded Pipeline in Oil &Gas: Pexgol Solution in Argentina

Efficient solution for transporting produced water with hydrocarbons under demanding conditions.

Estudo de Caso Nº

191

Cliente

Petróleos Sudamericanos
Argentina

|

2025

Condições de Trabalho

Temperature: 40°C / 104°F | Pressure: 10 kg/cm² | Fluid components: Water and hydrocarbons

Solução Pexgol

Pexgol 160 mm, class 15

Aplicação

Formation water transport

Comprimento

1140 m / 3740 ft

Categorias

Replacement of Corroded Pipeline in Oil &Gas: Pexgol Solution in Argentina

The Challenge

Petróleos Sudamericanos, an Argentine company focused on hydrocarbon exploration and production, faced an operational challenge at the Catriel Oeste field related to the transport of produced water containing hydrocarbons.

The existing infrastructure showed critical deterioration due to accelerated internal corrosion caused by the chemical nature of the fluid. This condition led to recurring failures in the pipeline, requiring welding repairs every six months. As a result, unplanned shutdowns occurred along with a continuous increase in maintenance costs, compromising the operational continuity of the system.

The project required transporting water with hydrocarbons at a temperature of 40°C and a pressure of 10 kg/cm² over a 1,140-meter pipeline using 160 mm (Class 15) pipe, under typical Oil & Gas operating conditions where system reliability is critical.

The Solution

To address this issue, a Pexgol (PE-Xa) piping system was implemented, selected for its high chemical resistance and its ability to operate reliably in aggressive environments. The solution eliminated the primary failure mechanism associated with corrosion, significantly extending the system’s service life and reducing the need for corrective maintenance.

The material’s flexibility and supply in long continuous lengths enabled a fast and efficient installation, minimizing the number of joints and potential failure points. The project execution was completed in just two working days, including pipe laying, installation of four mechanical couplings at critical points, and hydrostatic testing to ensure system integrity.

As a result, the operation achieved higher reliability, reduced operational costs, and eliminated unplanned shutdowns, positioning Pexgol as an efficient and long-term solution for fluid transport applications in the Oil & Gas industry.

Estudos de Caso Relacionados

A flexible and durable solution designed to adapt to pit benches, operate outdoors, and minimize connection work in difficult-to-access areas.

Safe Installation of a 355 mm Mine DewateringLine

MMG
Perú

 | 

2024
Drainage in Underground Mine with Slopes Between 40° and 90°.

Water Drainage in Underground Mine

NEMISA Mine
Mexico

 | 

2018
Transportation of Phosphoric acid in a potassium nitrate plant

Transportation of Phosphoric Acid

Haifa Chemicals
Israel

 | 

1995
Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Hot Caustic Line Replacement in Paper Mill

Pulp & Paper Mill

Svetlogorskiy Mill
Russia

 | 

2015
Transport Of Lime Slurry At 100°C

Transport of Lime Slurry

Minas de Oro Nacional, Mulatos Mine
Mexico

 | 

2015