Skip to content

Concentrated Copper Transportation

Lasta2 Filter Press Feed Lines

Estudo de Caso Nº

33

Cliente

BHP Billiton, Olympic Dam, Australia
Australia

|

2014

Condições de Trabalho

60°C, 9 bars.

Solução Pexgol

Pexgol 180, Class 15 / Pex-Lined Carbon Steel (PLCS) fittings.

Aplicação

Copper transportation.

Comprimento

Short sections.

Categorias

Lasta2 Filter Press Feed Lines

The Challenge

BHP used to transport concentrated copper, through a 6” rubber lined carbon steel (RLCS) and HDPE pipes that suffer from constant abrasion and corrosion.

From the maintenance point of view, repeating leaks were consuming too much time from the team, which could be allocated attending scheduled maintenance operations. So, they required a more resisting pipe material.

Pexgol Solution

Short sections of Pexgol pipe 180 mm, Class 15 with Pex-Lined Carbon Steel (PLCS) fittings were provided. The line installation took a day to layout and a day to assemble. The quick and secured flanged couplers allowed the team to work effectively in multiple locations of the line, without depending on a welding machine, or coordinating special safety zones. The line showed no leakage at start up.

Estudos de Caso Relacionados

Dewatering With Low Ph Levels

Open Cast Mine Dewatering

Arcelor Mittal Mine
Mexico

 | 

2016
Installation of a Drainage System between a Well and a Mining Dam.

Well Drainage at Mining Dam

CODELCO – El Teniente Mine
Chile

 | 

2019
Moving from PVC to Pexgol: Ensuring Efficiency in Lithium Production

Optimization of Lithium Brine Transportation

Puna Mining
Argentina

 | 

2022
Pexgol Pipe Installation for the Transport of Cyanide Water.

Transport of Cyanide Water

Equinox Gold
Mexico

 | 

2022
Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

Palm Oil: Transport of Leached Mud

Industria Chiquibul
Guatemala

 | 

2018
Transportation of water in more than 150 mining crossroads

Water Transport on Crossroads

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2012