Replacement of Carbon Steel Pipes by Pexgol Pipes for Tailing Lines.

Estudo de Caso Nº

63

Cliente

Ambatovy
Madagascar

|

2017

Condições de Trabalho

Pressure 800Kpa Slurry concentration of 35% solids Temperature 70°C to 80°C Composition (NH4) 2SO4 PH 6-8. Flow 3,200 m³/h (2.3 m/s)

Solução Pexgol

Pexgol 630 mm, Class 15

Aplicação

Slurry transportation

Comprimento

720 m

Categorias

Replacement of Carbon Steel Pipes by Pexgol Pipes for Tailing Lines.

The Challenge

Ambatovy for it nickel mine has 15 km of tailing lines. The tailing distribution lines are made of DN700 carbon steel and this pipelines suffered from repetitive and frequent failures.
This failures were because of the effect of erosion, mainly due to the high liquid velocities inside the pipeline, especially in those areas where there is slack flow in the line.
To a lesser extent, further thinning of the pipeline wall occurs, due the presence of the highly corrosive ammonium sulphate salt (NH4)2SO4 . The frequent failures prompted the decision to replace the the carbon steel tailing pipeline with Pexgol pipes.

Pexgol Solution

After designing the lines in cooperation with Paterson & Cook, Ambatovy decided to install Pexgol 630 mm pipes on 2017.

The pipes were installed down hill from the pumping station where velocities are high. Testing the wall thickness periodically showed minimum effect of wear on the installed Pexgol pipes.

Another advantage that Ambatovy pointed out as a reason to use Pexgol systems is the simplicity of dismantling and reinstalling Pexgol pipes when raising the dam’s level, which saves time and money if comparing this to doing it with carbon steel pipes or carboon steel lined pipes.

Estudos de Caso Relacionados

A Case Study on the Collaborative Engineering and Strategic Implementation of the Pexgol Pipeline System for Public Safety and Efficiency

Innovation in Safety: Pexgol Piping System for LPG Supply

Rawabi City
Israel

 | 

2010
Transport of Muddy Water (Pome) witha High Content of Organic Load.

Transport of Muddy Water in a Palm Oil Processing Plant

La Gloria
Colombia

 | 

2020
Test Installation for Transporting Silica Sand.

Transport of Silica Arena: HDPE vs Pexgol

Covia Corp
Mexico

 | 

2019
Pvc Pipe Replacement by Pexgol

Transportation of sodium sulfide

Magnelec S.A. de C.V.
Mexico

 | 

2018
Pexgol enabled a safe and efficient installation across a highly constrained refinery layout.

Nitrogen Transport in a Complex Industrial Environment

YPF
Argentina

 | 

2025
Water Extraction From Deep Wells (150 Meters)

Water Extraction from Wells

Andacollo Mine
Chile

 | 

2015