Skip to content

Environmental Protection and Efficiency in Tailings Management

In an engineering challenge, the Pexgol 225 mm (8”) Class 15 pipe proved to be the perfect solution for transporting tailings at the Mina Capela mining complex.

Estudo de Caso Nº

122

Cliente

Mina Capella – Grupo Peñoles
Mexico

|

2023

Condições de Trabalho

Flow: 200 m3/h Temperature: 25°C / 77°F Pressure: 130psi Fluid components: Limestone, water and acids – 55% solids in suspension. Specific weight 3. K50 (microns): 91.3

Solução Pexgol

Pexgol 225 mm (8″), Class 15

Aplicação

Transport of Slurry

Comprimento

900 m / 2952 ft

Categorias

Environmental Protection and Efficiency in Tailings Management

The Challenge

At the Mina Capela mining complex of Grupo Peñoles in Mexico, they faced the challenge of implementing an efficient and safe solution for pumping tailings from the thickener plant to a new tailings dam. The solution had to be wear-resistant in the long term and ensure minimal risk of leaks to protect the environment.

Pexgol Solution

The choice was to install 900 meters of Pexgol 225 mm (8”) Class 15 piping, known for its durability and abrasion resistance. The piping was arranged around the tailings dam, with branches every 200 meters to fill the dam from different positions, thus optimizing the distribution of material.

The main challenges to face were:

  • Highly abrasive fluid: The tailings required a solution that could withstand longterm
    wear.
  • Environmental protection: In case of spillage, the fluid could negatively affect
    the local ecosystem.

Therefore, an option with minimal risk of leaks in the piping and connections was sought.

The Pexgol 225 mm (8”) Class 15 piping proved to be the ideal solution for this challenge. The combination of the material’s (PE-X) abrasion resistance and the supply in rolls, which minimizes the number of joints, made Pexgol the safest option.

After three years of operation, thickness measurements taken every six months have confirmed that there has been no reduction in the thickness of the piping, demonstrating its durability and optimal performance.

Estudos de Caso Relacionados

Explore how Pexgol pipe replacement addressed the corrosion issue in Gordon Pool’s saltwater delivery system, ensuring efficient operation.

From Steel to Pexgol: A Plumbing Upgrade for Tel Aviv’s Gordon Pool

Gordon Pool
Israel

 | 

2023
Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE.

Pexgol Elbow for Slurry Transport

Antioquia Gold
Colombia

 | 

2022
High Pressure potable water line

High Pressure Potable Water Line

Antofagasta Minerals, Pelambres Mine
Chile

 | 

2014
Water Transportation through Shafts

Open Cast Mine Dewatering

Agnico Eagle Pinos Altos Mine
Mexico

 | 

2017
High-pressure water transport for the Southern Pit in a copper and zinc mine.

High-pressure fluid transport

Minera Antapaccay
Peru

 | 

2023
Water Transport from a Borehole with Low Ph.

Water transport in textile factory

CMT La Laguna
Mexico

 | 