Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

Pexgol’s resistance to scaling and chemicals delivers consistent operation in open-pit mining.

Estudo de Caso Nº

176

Cliente

Buena Vista del Cobre
Mexico

|

2024

Condições de Trabalho

Temperature: Ambient (Design temp. 40°C) | Pressure: 160–180 psi | Flow Rate: 335 m³/hr | Fluid Composition: Molybdenite (MoS₂) in copper-molybdenum concentrate, with Mo, Cu, Fe, S, and Si

Solução Pexgol

Pexgol 8″ SDR 11

Aplicação

Molybdenum concentrate flotation

Comprimento

100 m / 328 ft

Categorias

Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

The Challenge

At the Buena Vista del Cobre open-pit mine in Sonora, Mexico, molybdenum concentrate was transported through an HDPE pipeline. This system was regularly compromised by the highly scaling nature of the fluid, which consisted primarily of molybdenite (MoS₂) in a copper-molybdenum concentrate containing Mo, Cu, Fe, S, and Si.

The HDPE pipelines required daily manual intervention to prevent blockages, including frequent hammering along the line to maintain flow. Additionally, sections of the pipe had to be replaced at least once a month due to severe scaling buildup—resulting in high maintenance costs, operational delays, and recurring shutdowns.

The Solution

In 2024, the mine replaced 100 meters of 8” SDR 11 HDPE pipe with Pexgol pipe for its molybdenum concentrate flotation line. Pexgol was selected for its exceptional chemical and corrosion resistance, and especially its superior performance against scaling—a crucial feature given the aggressive nature of the transported slurry and the system’s operating conditions (160–180 psi pressure and temperatures up to 40°C).

The installation was fast and simple, requiring no specialized equipment. The Pexgol coil was unrolled using an excavator and front loader, and the pipe was laid in place within hours. Only electrofusion couplings (EF) were used, further simplifying the process.

Results

After one year of continuous operation, the client reported zero blockages and no maintenance required on the Pexgol line. This has eliminated the need for frequent replacements and cleaning, drastically reducing operational costs and ensuring uninterrupted flotation processes that meet Grupo México’s high efficiency standards.

Estudos de Caso Relacionados

Installation of Buried Pipes to Transport Water on a Mining Road.

Water Transportation on a Mining Road

CODELCO – Andina Mine
Chile

 | 

2019
Dewatering With Low Ph Levels

Open Cast Mine Dewatering

Arcelor Mittal Mine
Mexico

 | 

2016
Potable Water Supply on Harsh Terrain

Potable Water Supply on Harsh Terrain

Mekorot / Beit Shemesh Water Company
Israel

 | 

2017
Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Transporting Brine at High Pressure

Mekorot
Israel

 | 

2020
High Pressure potable water line

High Pressure Potable Water Line

Antofagasta Minerals, Pelambres Mine
Chile

 | 

2014
Pexgol’s proposal was clear - to provide a pipe that showcased superior wear resistance, estimated to be three times more durable than HDPE.

Transforming Tailings Transport: The Pexgol Advantage

Lundin Mining
Chile

 | 

2021