Skip to content

Fish Discharge Lines

Installation of Pexgol Pipes to Transport Fish.

Estudo de Caso Nº

71

Cliente

TASA
Peru

|

2018

Condições de Trabalho

Extreme temperatures 5° to 21°C / 41° to 69.8°F

Solução Pexgol

Pexgol 355 mm (14”), class 10

Aplicação

Fish transport

Comprimento

2100 m / 6900 ft

Categorias

Installation of Pexgol Pipes to Transport Fish.

The Challenge

Tecnológica de Alimentos S.A. (TASA) required to transport Anchovy fish that measured between 12 and 15 cm from their vessels to the processing plant.

The fish was transported using HDPE pipes. The fish lost it mass due to rubbing against the walls of the pipes. These pipes were joined by thermofusion, which caused an internal burr (protruding portion of material) in the joints and increased damage to the fish. For this reason 450 mm HDPE pipes and a large amount of water must be used to transport the fish. The latter caused a considerable increase in the costs of water treatment.

Pexgol Solution

The client decided to replace its HDPE pipes and install 4 Pexgol lines for fish unloading in 3 plants of the company, with a length of 700 meters each and a diameter of 355 mm (14”) class 10. In the installation, concrete pieces were put on the pipe in order to make sure it doesn’t float on the sea.

Among the main advantages that were verified in this application were:

  • Smooth internal surface: Decreased mass loss, which results in the fish practically intact at the exit of the discharge, and therefore generates a better quality final product.
  • Lower costs for water treatment: It was possible to lower HDPE pipes of 450 mm PN 10 to Pexgol 355 mm (14”) class 10 pipes. Since it is a less rough pipe material, it allows the fish to be transported with less water, reducing more than 20% the cubic meters of water per linear meter.
  • Electrofusion unions: 178 unions were made that did not leave any type of internal burr (and therefore generate less damage to the fish).

Estudos de Caso Relacionados

Pexgol’s Piping Solution for Regal Petroleum.

Overcoming Piping Challenges in Hydrocarbon Transportation

Regal Petroleum Corporation
Ukraine

 | 

2023
A Case Study on the Collaborative Engineering and Strategic Implementation of the Pexgol Pipeline System for Public Safety and Efficiency

Innovation in Safety: Pexgol Piping System for LPG Supply

Rawabi City
Israel

 | 

2010
Bridging the Gap between Durability and Functionality in Harsh Processing Environments.

Syncrude & Pexgol: A Collaboration Set to Reshape Slurry Transport

Syncrude
Canada

 | 

2022
Boosting Productivity and Reducing Maintenance in Livestock Feed Production.

From Steel Struggles to Pexgol Progress

Ambar
Israel

 | 

2022
Installation of Pexgol Pipes for Drainage of an Underground Mine

Vertical Drain in Underground Mine

Meridian Mine - Faena El Peñón
Chile

 | 

2018
How Pexgol Accelerated the Supply and Installation of a Critical Line.

Comprehensive Water Transportation Solution for Urgent Projects

Madagascar Mining
Madagascar

 | 

2024