Hot & Abrasive Potash Brine Processing

Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Estudo de Caso Nº

87

Cliente

Fertilizer Company
Canada

|

2017

Condições de Trabalho

Temperature: 96°C / 204°F

Solução Pexgol

Pexgol 450 mm (18”), class 24 | Pexgol 400 mm (16”), class 15

Aplicação

Hot Ore and Brine Processing

Comprimento

400 m / 1312.34 ft

Categorias

Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

The Challenge

A Canadian fertilizer company, and the largest producer of potash and the third largest producer of nitrogen fertilizer in the world, required to transport hot ore and brine in their facility in Saskatoon, Saskatchewan.

This was a new intake line. The facility traditionally used FRP and rubber-lined steel pipes. The FRP stress cracking issues and failure mechanism were a concern, and the client wanted to move away from it, but the conditions made material selection challenging.

The new line required to been able to transport saturated chloride brine at elevated temperatures with high resistance to abrasive slurries.

Pexgol Solution

The design of the line was carried out by the engineering company Wood Plc (then AMEC-FW) and Pexgol was selected. Pexgol went through several verification stages to ensure material suitability and verify design parameters:

  • Temperature and pressure suitability.
  • Abrasion resistance comparison with FRP, PP-RCT and other materials.
  • Expansion restraining forces analysis.
  • Support Distance Verification.

The system required a variety of nonstandards elbows, which were made by Golan’s Application Team.

The reliability of Pexgol during the last years has motivated the client to continue with their material reliability improvements in other parts of the facility, and other sites.

Estudos de Caso Relacionados

Potable Water Supply on Harsh Terrain

Potable Water Supply on Harsh Terrain

Mekorot / Beit Shemesh Water Company
Israel

 | 

2017
High Pressure Water Transport for a Gold Mine.

High Pressure Water Transport

Mansfield Mine
Argentina

 | 

2019
Pvc Pipe Replacement by Pexgol

Transportation of sodium sulfide

Magnelec S.A. de C.V.
Mexico

 | 

2018
Transportation of water with solids from an open cast mine

Open Cast Mine Dewatering

Doña Inés de Collahuasi SCM, Collahuasi Mine
Chile

 | 

2013
A high-precision maneuver enabled the complete assembly of the system in record time, ensuring safety and operational continuity.

Pexgol Overcomes Extreme Dewatering Conditions in La Ciénega

Fresnillo Plc.
Mexico

 | 

2025
Delivering Durability and Flexibility for a Sustainable Approach to Space Access.

Pioneering Space Launches with Ground-breaking Piping Solutions

SpinLaunch
USA

 | 

2021