Hot & Abrasive Potash Brine Processing

Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Estudo de Caso Nº

87

Cliente

Fertilizer Company
Canada

|

2017

Condições de Trabalho

Temperature: 96°C / 204°F

Solução Pexgol

Pexgol 450 mm (18”), class 24 | Pexgol 400 mm (16”), class 15

Aplicação

Hot Ore and Brine Processing

Comprimento

400 m / 1312.34 ft

Categorias

Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

The Challenge

A Canadian fertilizer company, and the largest producer of potash and the third largest producer of nitrogen fertilizer in the world, required to transport hot ore and brine in their facility in Saskatoon, Saskatchewan.

This was a new intake line. The facility traditionally used FRP and rubber-lined steel pipes. The FRP stress cracking issues and failure mechanism were a concern, and the client wanted to move away from it, but the conditions made material selection challenging.

The new line required to been able to transport saturated chloride brine at elevated temperatures with high resistance to abrasive slurries.

Pexgol Solution

The design of the line was carried out by the engineering company Wood Plc (then AMEC-FW) and Pexgol was selected. Pexgol went through several verification stages to ensure material suitability and verify design parameters:

  • Temperature and pressure suitability.
  • Abrasion resistance comparison with FRP, PP-RCT and other materials.
  • Expansion restraining forces analysis.
  • Support Distance Verification.

The system required a variety of nonstandards elbows, which were made by Golan’s Application Team.

The reliability of Pexgol during the last years has motivated the client to continue with their material reliability improvements in other parts of the facility, and other sites.

Estudos de Caso Relacionados

The Robust & Flexible Answer to Constantly Changing Mine Surfaces.

Evolving Mine Operations with Pexgol Piping

Peña Colorada
Mexico

 | 

2023
Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Installation of a Borehole with Pipe in Sections for Reduced Space.

Installation of Water Well in Reduced Space

Mekorot
Israel

 | 

2020
Test Of Pexgol Pipes Vs Hdpe Pipes For Brine Transportation

Test: Pexgol vs HDPE for Brine Transportation

YBL
Bolivia

 | 

2017
Water line feed from wells to mine

Water Lines – High Pressure Water Feed Lines

Yamana Gold, Meridian Mine
Chile

 | 

2012
Trial Demonstrates Superior Wear Resistance in Sea Water + Ash Slurry Conditions.

Unmatched Durability in Harsh Slurry: Pexgol Outperforms Steel

Tata Power
India

 | 

2023