Meltdown Water Transport
Pipe installation on a mountain
Estudo de Caso Nº
16
Cliente
Codelco Andina, TADA 1-2 Project
Chile
|
2013
Condições de Trabalho
Complex & harsh ground, 300 m altitude.
Solução Pexgol
Pexgol 315 mm, Class 15 (SDR 11).
Aplicação
Water transportation.
Comprimento
3,300 m.
Categorias

The Challenge
Codelco needed to transport meltdown water downhill at Andes Mountain range.
The water pipes installation was a big risk for the team, as well as huge workforce with short time schedules.
Pexgol Solution
Using hoses seemed to be the solution, but the complexity of its installation made the client decided to use Pexgol in long sections instead.
The installation was simplified by the use of Pexgol long sections.
The pipes were unrolled from it coils and jointed trough electro-fusion, to be dragged and mapped out according to the project.
The installation was done in perfect timing with an optimal performance.
Estudos de Caso Relacionados
Leached Slurry Transportation
Moa Nickel S.A. Sherritt
Cuba
|
2013
Streamlining Effluent Treatment with Pexgol
Pan American Energy
Argentina
|
2023
Pexgol Piping for Fire Network System Expansion
Wall
Argentina
|
2023
Compressed Air Transportation
Saucito S.A. de C.V. Mine
Mexico
|
2017