Mine Dewatering at Low Temperature

Vertical Mobile Pexgol Installation on the Rocks for Mine Dewatering.

Estudo de Caso Nº

61

Cliente

Ferrexpo Yeristovo Mining
Ukraine

|

2019

Condições de Trabalho

Vertical installation, ground laying on hills. Ambient temperature: -15°C to 4°C

Solução Pexgol

Pexgol 280 mm (10”), Class 15

Aplicação

Mine Dewatering

Comprimento

360 m

Categorias

Vertical Mobile Pexgol Installation on the Rocks for Mine Dewatering.

The Challenge

Ferrexpo Yeristovo Mining needed to install mobile long sections of pipeline for mine dewatering. They requested that the pipe should have scratch resistance and can be installed on the rocks without any complicate preparations.
They used to work with steel pipes but they presented serious problems such as:

  1. Corrosion
  2. Difficult and expensive installation
  3. Long disassembly and replacement time

Pexgol Solution

The client chose Pexgol pipes with 280 outside diameter, class 15 in coils of 120 meters each with mechanical couplers for a fast and efficient installation. During the installation a 60 ton Hitachi bulldozer and a Manitou telehandler were used for decoiling.

There were 3 separated lines of one piece of 120 meters each without any additional connectors. The only connection was a flange coupler with a pump outlet. Pipes were fixed on top and in the middle by fixpoint clamps as well.

The use of Pexgol pipe solutions allow the client to save costs (manpower and installation time).

Estudos de Caso Relacionados

Transforming water transportation with Pexgol technology

Pexgol’s Solution for CFE: A Leap in Durability and Efficiency

Comisión Federal de Electricidad
Mexico

 | 

2023
Installation of a New Pexgol Pipeline to Provide Hot Water for a Electro-Thermal Storage System.

Hot Water Distribution for Solar Technology

Raygen
Australia

 | 

2021
Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Installation of a Pexgol Elbow with Mechanical Joints to Replace HDPE.

Pexgol Elbow for Slurry Transport

Antioquia Gold
Colombia

 | 

2022
Transport of Leached Mud from the Treatment Plant to an Oxidation Lagoon

Palm Oil: Transport of Leached Mud

Industria Chiquibul
Guatemala

 | 

2018
Replacement of HDPE Pipe for Pexgol

Slurry Transportation

Tizapa Mine
Mexico

 | 

2015