Skip to content

Overcoming Geotechnical Challenges with Pexgol at Media Luna

Improving drainage in the Media Luna mine with Pexgol.

Estudo de Caso Nº

159

Cliente

Minera Media Luna
Mexico

|

2023

Condições de Trabalho

Temperature: 25°C / 77°F | Flow: 80 l/sec | Pressure: 28.5 bar

Solução Pexgol

Pexgol 8″ SDR 6

Aplicação

Mine Dewatering

Comprimento

540 m / 1640.42 ft

Categorias

Overcoming Geotechnical Challenges with Pexgol at Media Luna

The Challenge

Torex Gold, an intermediate gold producer with operations in the Guerrero gold belt in Mexico, faced a significant challenge at its Media Luna mine. The need for an effective underground water pumping system was critical to continuing mining operations. The conventional alternative of using steel pipes presented multiple disadvantages, including the high cost of installation and materials, the need for frequent welding every 12 meters, and the requirement for specialized machinery for installation inside the mine, in addition to susceptibility to corrosion due to high humidity in the underground environment.

The Solution

After a thorough analysis, Torex Gold selected 8” SDR 6 Pexgol pipes for a total of 540 metres distributed in two coils of 270 metres each. Pexgol pipes were chosen for their corrosion resistance, the possibility of supplying them in long sections that significantly reduce joints, and their fast and efficient installation. In addition, the lightness and flexibility of the material facilitated its handling and installation in the complex mine environment.
The implementation of the Pexgol solution at Minera Media Luna not only met the operational and technical requirements of the project, but also exceeded expectations in terms of installation efficiency and costs. The ability to supply pipes in long coils allowed for continuous installation without the interruptions and costs associated with welding required by steel pipes. In addition, the mine’s in-house engineering successfully designed the surface base and the clamping platform at the end of the countershaft, ensuring seamless integration of the Pexgol system into the existing infrastructure. This project not only demonstrated the technical and economic viability of Pexgol pipes in challenging mining applications, but also set a precedent for future implementations, highlighting the importance of selecting innovative materials that offer durable and cost-effective solutions in the mining industry.

Estudos de Caso Relacionados

Transport of Drinking Water in Harsh Terrain.

Potable Water Aqueduct

Acueducto y Alcantarillado de Bogotá
Colombia

 | 

2019
Transport of acid slurry at high temperatures

Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2012
Adapting to the demands of the process: how Pexgol solves the problems of corrosion and abrasion in the extraction of palm oil.

Implementation of Pexgol Pipelines for the Transport of Muddy Water

IACSA
Colombia

 | 

2023
Installation of Pexgol pipes for the transport of formation water (gas and minerals)

Gas Wells: Formation Water Treatment

Canacol
Colombia

 | 

2018
Installation of Pexgol Pipe to Transport Brine at High Pressure in a Borehole.

Transporting Brine at High Pressure

Mekorot
Israel

 | 

2020
Reduced wear and increased durability in the sand cleaning process at KSB de México.

Improving efficiency in steel foundry with Pexgol

KSB de Mexico
Mexico

 | 

2023