Skip to content

Pexgol Simplifies Slurry Transportation at Buriticá Mine

Reducing maintenance and increasing safety in hydraulic backfill operations.

Estudo de Caso Nº

166

Cliente

Zijin – Continental Gold
Colombia

|

2023

Condições de Trabalho

Temperature: 25°C / 77°F | Pressure: 8 bar | Fluid Components: Sand, water, cement (70% solids)

Solução Pexgol

Pexgol 160 mm, class 15

Aplicação

Slurry transport for hydraulic backfill

Comprimento

70 m / 229.65 ft

Categorias

Pexgol Simplifies Slurry Transportation at Buriticá Mine

The Challenge

Zijin-Continental Gold, operator of the Buriticá Mine in Colombia, faced a significant challenge in transporting slurry for hydraulic backfill—a complex application due to the abrasive and scaling nature of the fluid, composed of sand, cement, and water.

The previously used HDPE pipes suffered from wear, leakage at connections, and installation difficulties in the underground environment, characterized by limited space, lack of lighting, and scarce resources. A more durable and efficient solution was clearly needed, especially in the section between levels 1140 and 1105, where the velocity on
the slope increased wear on the pipes.

The Solution

To tackle these issues, 160 mm, class 15 Pexgol pipes were installed in a section of the project. Pexgol was selected for its high abrasion resistance and because it is supplied in coils of up to 600 meters, ensuring safe and efficient
installation. The installation was completed over two shifts: during the first shift, the pipe was uncoiled, and in the second shift, it was lowered through the ventilation shaft, with the support system placed at the back of the setup, and transition joints between steel and Pexgol made using flanged couplings.

The implementation of Pexgol pipes at the Buriticá Mine resulted in a quick and efficient installation, eliminating the wear and leakage issues that affected the HDPE pipes. The flexibility of the material allowed for easy adaptation to the underground conditions, with supports required only every 3 meters in the horizontal section and no need for supports in the vertical section. This solution not only improved the durability and efficiency of the slurry transport system but also significantly reduced maintenance costs and enhanced operational safety.

This collaboration highlights how technological solutions can transform mining operations, improving both productivity and safety.

Estudos de Caso Relacionados

Biodiesel Transport through the Colombian Jungle

Biodiesel Transport

Indupalma (Oro Rojo Plant)
Colombia

 | 

2012
Pexgol’s resistance to scaling and chemicals delivers consistent operation in open-pit mining.

Switch to Pexgol Reduces Downtime in Molybdenum Concentrate Transport

Buena Vista del Cobre
Mexico

 | 

2024
Transport of acid slurry at high temperatures

Slurry Transportation

Moa Nickel S.A. Sherritt
Cuba

 | 

2012
High Pressure potable water line

High Pressure Potable Water Line

Antofagasta Minerals, Pelambres Mine
Chile

 | 

2014
Installation of Pexgol Pipesf for the Drainage of an Underground Mine.

High Pressure Drain in Underground Mine

Ojos del Salado Mine – Lundin Mining
Chile

 | 

2018
A Case Study on the Collaborative Engineering and Strategic Implementation of the Pexgol Pipeline System for Public Safety and Efficiency

Innovation in Safety: Pexgol Piping System for LPG Supply

Rawabi City
Israel

 | 

2010