Recovered Water Transportation

Grey Water Transportation

Estudo de Caso Nº

38

Cliente

Coeur Mexicana S.A. de C.V. Palmarejo
Mexico

|

2017

Condições de Trabalho

74 psi, altitude dierence= 34 m, Au= 0.12 ppm, Ag= 0.18 ppm, Cu= 1.13 ppm, Fe= 0.73 ppm, Cn total= 1.5 ppm, Ca= 458 mg/dL, Ph= 8

Solução Pexgol

Pexgol SDR 15 225 x 20.4.

Aplicação

Water transportation.

Comprimento

1200 meters.

Categorias

Grey Water Transportation

The Challenge

Coeur Mexicana required to transport recovered water, but they wanted to conduct an installation in the minimum time possible that won’t require contractors, specialized personnel neither expensive equipment.

Pexgol Solution

The client decided to install Pexgol, due to it quick and easy installation, that if was carried out with steel or HDPE pipes, it would require 100 joints. But, since it was done with Pexgol pipes it only took 4 joints.

Furthermore, it was considered the security that Pexgol pipes offer, since it’s supplied in long length coils, which reduces leakages.

Pexgol’s team advised the client during the whole process from the design to the installation.

Estudos de Caso Relacionados

Pexgol Pipe for the Transport of Fluorosilicic Acid.

Fluorosilicic Acid Transport

Phosphate Mine – ICL Rotem
Israel

 | 

1995
Pexgol Pipe to Transport Effluents at 30°C / 86°F in an Underground Mine.

Pumping Mining Effluents

AngloGold Ashanti
Brazil

 | 

2019
Dry Gas Line for Pump Activation.

Dry Gas Transportation

ExxonMobil
Argentina

 | 

2020
Food Transport Pexgol vs HDPE

Food Transport Pexgol vs HDPE

Marine Farms
Chile

 | 

2017
Installation of Pexgol Pipesf for the Drainage of an Underground Mine.

High Pressure Drain in Underground Mine

Ojos del Salado Mine – Lundin Mining
Chile

 | 

2018
Lasta2 Filter Press Feed Lines

Concentrated Copper Transportation

BHP Billiton, Olympic Dam, Australia
Australia

 | 

2014