Condições de Trabalho

Temperature: 40° / 104°F | Flow: 100 m³/d | Pressure: 30 kg/cm² | Fluid components: Formation water

Solução Pexgol

Pexgol 90 mm class 15; 90 mm class 24 & 110 mm class 30

Aplicação

Secondary Recovery

Comprimento

700 m / 2296.59 ft

Categorias

Pexgol’s Solution in Secondary Recovery for EMESA

The Challenge

EMESA, an energy company in the province of Mendoza (Argentina) that participates in some hydrocarbon projects in the province in collaboration with private operators, faced the need to establish a new line for secondary recovery. The project involved transporting formation water from a well with mechanical pumping (AIB) to a tank, operating at a temperature of 40°C, a flow rate of 100 m³/h, and a pressure of 30 kg/cm².

The Solution

To meet the operational requirements of the project, EMESA decided to implement 90 mm class 15, 90 mm class 24, and 110 mm class 30 Pexgol pipes, covering a total length of 700 meters. Pexgol pipes were selected due to their quick installation, material flexibility, lightness, and ease of handling, as well as their ability to supply long sections that simplify the installation process.

The installation of the Pexgol pipes was efficiently carried out in a single day by unrolling the pipes and using double mechanical connectors and flanged couplings. This process was not only fast but also notable for the minimal time required for the installation of mechanical fittings. Pexgol’s ability to handle high pressures and temperatures,
along with its corrosion resistance, ensured reliable and long-lasting operation.

EMESA’s positive experience with Pexgol underscores the importance of choosing high-quality and resistant materials for critical applications in the energy sector

Estudos de Caso Relacionados

Drainage in Underground Mine with Slopes Between 40° and 90°.

Water Drainage in Underground Mine

NEMISA Mine
Mexico

 | 

2018
Installation of 3000 Meters Of PE-X Pipe for an Underground Mine.

Drainage Lines in Underground Mine

Lundin Mining – Candelaria Norte Mine
Chile

 | 

2020
Installation of Pexgol Pipe for a Intake Line to Transport Hot Abrasive Brine Slurries

Hot & Abrasive Potash Brine Processing

Fertilizer Company
Canada

 | 

2017
Transportation of brackish water to the main pumping station

Water Lines – Harsh Conditions

Dead Sea Works
Israel

 | 

1993
Overcoming Corrosion Challenges in the Oil Industry

Overcoming Corrosion Challenges in the Oil Industry

Petróleos Sudamericanos
Argentina

 | 

2023
High Pressure Water Transport for a Gold Mine.

High Pressure Water Transport

Mansfield Mine
Argentina

 | 

2019