Process Water – Brine Transportation

Scale build up reduction - highly concentrated lime solution

Estudo de Caso Nº

7

Cliente

SQM Nueva Victoria-Iquique
Chile

|

2010

Condições de Trabalho

Corrosion and material build-up with high concentration.

Solução Pexgol

Pexgol 315 x 28.6, Class 15.

Aplicação

Transport of highly concentrated brine solution.

Comprimento

12 meters.

Categorias

Process Water - Brine Transportation

The Challenge

As the solution was being pumped, calcium carbonate deposits caused clogging in the existing HDPE pipe wall in both the straight parts of the circuit as well as the elbows. This clogging prevented the evaporation pools from receiving the required amount of lime water. Clogs formed every 2 months, affecting production.

The plant’s operators needed to reduce this effect or eliminate it by replacing the pipe with another.

Pexgol Solution

Due to the replacement of HDPE pipes with the smooth internal surface of Pexgol’s pipes, clogs were completely eliminated. In addition, the production and transportation of the new pipes in coils reduced the number of joints, which was a major source of deposition.

A Pexgol pipe was installed between two HDPE pipes and connected by Vitaulic joints 994. After two months the pipes were removed for inspection and no deposition was found, while the HDPE pipe did.

Since the installation of the new pipes in 2010, the original Mean Time Between Failures (MTBF) of the HDPE pipes – of two months – has been completely eliminated. Pexgol’s pipes have never failed or clogged.

Estudos de Caso Relacionados

Installation of 1000 Meters of PE-X Pipe for an Underground Mine.

Mining Drainage Lines

Lundin Mining – Alcaparosa Mine
Chile

 | 

2019
Replacement of Carbon Steel Pipes by Pexgol Pipes for Tailing Lines.

Tailing Lines

Ambatovy
Madagascar

 | 

2017
Pexgol: Delivering Rapid, Reliable & Long-lasting Mining Drainage Solutions

Addressing Drainage Challenges with Pexgol

Avino Mine
Mexico

 | 

2023
Pexgol Transforms Tailings Transportation at Minera San Julián.

Minera San Julián Adopts Pexgol to Improve Water Management

Fresnillo plc
Mexico

 | 

2024
Installation of Pexgol Pipe in a Formation Water Treatment Plant.

Secondary Injection Water Plant

YPF
Argentina

 | 

2020
Water line feed from wells to mine

Water Lines – High Pressure Water Feed Lines

Yamana Gold, Meridian Mine
Chile

 | 

2012